26.Depreciation ____ expenses reported and ____ taxes paid.
A. Increases, increases
B. Increases, decreases
C. Decreases, decreases
D. Decreases, increases
26.折旧将会报告的支出并缴纳的税额。
A.增加;增加
B.增加;降低
C.降低;降低
D.降低;增加
27.You have used several cash flow methods to determine alternativeways of performing your current project. You know which of the following is true regarding the results ofyour cash flow analysis?
A.Payback period and IRR will generally give you the sameaccept/reject decision.
B.NPV and discounted cash flows will generally give you the sameaccept/reject decision.
C.Payback period and discounted cash flows will generally give you thesame accept/reject decision.
D.NPV and IRR will generally give you the same accept/reject decision.
27.你用到几种现金流方法来决定当前项目的替换方案,你的现金流分析的结果中,下面哪种陈述是正确的?
A.回收期和内部收益率将产生相同的接收/拒绝的决策
B.净现值和贴现现金流将产生相同的接收/拒绝的决策
C.回收期和贴现现金流将产生相同的接收/拒绝的决策
D.净现值和内部收益率将产生相同的接收/拒绝的决策
28.You are a member of a large government project. You know that the contract insiststhat all equipment be manufactured in the United States. You see a senior member of yourteam replacing a company etching on a piece of equipment that was made in aforeign country. You confrontthis person, and he says he is following the project manager’s orders. What should you do?
A.Nothing; the project manager made the decision.
B.Immediately report the violation to the government.
C.Update your resume and look for another job.
D.Talk to the project manager about the situation, and then decidewhat to do.
28.你是一个大型政府项目的成员。你知道合同规定所有设备必须在美国生产。你看到团队中一个资深成员正在用国外生产的一件设备来替换锈蚀的配件。你面对这个人提出问题,他说他按照项目经理的指令做的,你应该:
A.不做什么,项目经理做的决策。
B.立即向政府报告。
C.更新你的简历找新的工作。
D.和项目经理交流这个情况,再作决定。
29.Which process is the foundation process within the Risk Managementknowledge area that helps establish risk management for all the processes thatfollow?
A.Risk Monitoring and Control
B.Risk Response Planning
C.Risk Management Planning
D.Risk Identification
29.在风险管理知识领域,哪一个过程有助于确立风险管理其他所有过程的管理?
A.风险监控
B.风险应对规划
C.风险管理规划
D.风险识别
30. If EV = 145, PV = 162, AC = 138, BAC = 200, what is EAC when youbelieve current variances are not typical?
A.201
B.190.4
C.193
D.200
30.如果EV=145,PV=162,AC=138,BAC=200,而且当前的偏差并非典型情况,那么EAC应为:
A.201
B.190.4
C.193
D.200
31. You need to decide between two alternatives. You can either hire a contractorto build one of the project’s deliverables, or you can buy the deliverable froman overseas supplier. Both options require acquisition, operating, and disposal coststhat you compare between the two alternatives to make a decision. What is this technique called?
A.Value Engineering
B.Life cycle costing
C.Earned Value Management
D.Financial analysis
31.你需要决定两个方案,你可以雇佣一个承包商来建设项目的交付成果,也可以从海外供应商那里购买。你需要比较两个方案的获取、运营和处置成本,以便作出决策。这种技术称为:
A.价值工程
B.生命期成本
C.挣值管理
D.财务分析
32.You are managing a project team with several highly educatedprofessionals. One of yourteam members has requested to work from home two days a week. What should you do?
A.Consult your human resource office to discuss company policies andprocedures first.
B.To be fair, issue a policy that no team members can work from home.
C.If the person is a good worker, approve the request.
D.To be fair, issue a policy that all team members can work from home.
32.你管理着一个团队,有几个高级专家。你的一个队员希望一个星期在家工作两天,你怎么办?
A.首先和人力资源办公室协商,讨论公司政策和程序
B.公平起见,发布一个不许在家工作的政策
C.如果他是个好员工,批准这个请求
D.公平起见,发布一个人人都可以在家工作的政策
33.You have received estimates for one of your project tasks asfollows: The pessimistic estimate is 24 days, the optimistic estimate is 18days, and the most likely estimate is 20 days. What is the standard deviation?
A.1
B.0.33
C.0.67
D.1.5
33.你收到项目任务的估算如下,最悲观24天,最乐观18天,最可能20天,一个标准差是多少?
A.1
B.0.33
C.0.67
D.1.5

相关试题:

PMP美国项目管理认证模拟预测习题2

PMP考试全真模拟题及答案(样题)

PMP模拟习题汇总(附参考答案)

添加应用,免费套题体验

视频学习

我考网版权与免责声明

① 凡本网注明稿件来源为"原创"的所有文字、图片和音视频稿件,版权均属本网所有。任何媒体、网站或个人转载、链接转贴或以其他方式复制发表时必须注明"稿件来源:我考网",违者本网将依法追究责任;

② 本网部分稿件来源于网络,任何单位或个人认为我考网发布的内容可能涉嫌侵犯其合法权益,应该及时向我考网书面反馈,并提供身份证明、权属证明及详细侵权情况证明,我考网在收到上述法律文件后,将会尽快移除被控侵权内容。

最近更新

社区交流

考试问答