18.You have just passed the PMP exam. Your friend is still studying and plans on taking the exam nextmonth. Youpurchased a copy of this book to study from, while your friend purchased a copyof another author’s book. Since you’re finished studying, you agree to loan your book withthe CD to your friend so she can use it to study from also. Which of the following statementsis true?
A.Since you are a PMP, you’re required to adhere to the PMP Code ofProfessional Conduct, so sharing the book and CD is not acceptable.
B.Since you are a PMP, you should not share the book and CD with yourfriend, because it may pose a conflict of interest for your friend.
C.The book and CD are considered intellectual property and should notbe copied. However,loaning your copy to your friend to use, as long as she doesn’t copy it, isacceptable.
D.Since you are a PMP, you’re required to adhere to the PMP Code ofProfessional Conduct and should not share the book and CD with your friendbecause of the appearance of impropriety.
18.你刚刚考过了PMP,你的朋友准备下一个月考PMP。你买了一本书来学习,而你的朋友买了另一种书。你已经学完了,所以你打算把你的书和书上的CD借给你的朋友学习。下面哪一种说法是正确的?
A.既然是PMP,就要遵守行为规范,所以不能借
B.既然你是PMP,就不要借书和CD给你的朋友,你们有利益冲突
C.书和CD都是知识产权,所以是不能拷贝的。只要不复制,借给朋友使用是可以接受的。
D.既然是PMP,就要遵守行为规范,所以不能共享书和CD,因为这属于行为不当。
19.All of the following are true statements regarding the QuantitativeRisk Analysis process except for which one?
A.This process uses decision tree analysis, which is a type ofsensitivity analysis.
B.This process determines the size of the schedule and costcontingency reserves.
C.This process helps determine the probability of achieving theproject objectives.
D.This process generally follows Qualitative Risk Analysis but can beperformed separately if desired.
19.关于风险定量分析出了哪一个之外都是正确的?
A.这一过程使用决策树分析,它是敏感性分析的一种。
B.这一过程决定了进度和成本的应急储备。
C.这一过程有助于确定实现项目目标的概率。
D.这一过程通常在风险定性分析之后进行,但也可以单独进行。
20.You are using the interviewing technique of the Quantitative RiskAnalysis process.Theprobability distribution you intend to use is triangular distribution.All of the following statements aretrue regarding this question except:
A.Interviewing techniques are used to quantify the probability andimpact of the risks on project objectives.
B.The information gathered depends on the type of probabilitydistribution used.
C.The triangular distribution typically uses symmetrical discretedistribution.
D.Triangular distributions rely on mean and standard deviation toquantify risks.
20.你在风险定量分析过程使用访谈技术,你打算使用的概率分布是三角分布。下面哪一个说法是错误的?
A.访谈技术应用于项目目标风险的概率和后果的量化
B.收集的信息取决于所选用的概率分布类型
C.三角分布典型的使用对称的非持续性概率分布
D.三角分布依靠平均值和标准差来量化风险
21.All of the following statements are true regarding the timeconstraints of imposed dates and key events except:
A.Imposed dates and key events constraints are inputs to integratedchange control process.
B.Imposed dates apply to activities that must start no later than orfinish no later than a specific date.
C.The key events time constraint applies to the completion ofdeliverables by the requested date of a stakeholder.
D.Requested completion dates often become expected dates and thereforepose a time constraint.
21.关于时间约束中的强加日期和关键事件,那个说法是错误的?
A.强加日期和关键事件是整体变更控制过程的输入
B.强加日期应用于其开始或完成日期不得迟于某一指定日期的那些活动
C.关键事件约束是指干系人所要求的完工活动的期限
D.请求的完工日期经常成为预期的完工日期,因此成为时间约束
22.This win-win conflict resolution technique is the one that projectmanagers should use most.
A.Confrontation
B.Compromise
C.Withdrawal
D.Smoothing
22.一种项目经理最常用的双赢的矛盾解决方法是:
A.对撞
B.让步
C.撤退
D.缓和
23.You are working with a group of managers to decide which projects topursue. Cost is animportant consideration. Which type of costs should not be a criteria in project selection?
A.Indirect costs
B.Sunk costs
C.Tangible costs
D.Intangible costs
23.你和一个经理团队一起决定进行哪一些项目,成本是重要的考虑因素,下面哪一项不是项目选择的标准?
A.直接成本
B.沉没成本
C.有形成本
D.无形成本
24.One of your team members, a fellow PMP, is under investigation forviolation of the PMP Code of Professional Conduct . What action should you take?
A.Cooperate fully with PMI in the investigation.
B.Tell PMI it would be a conflict of interest for you to cooperate inthe investigation, because this person is your team member.
C.Tell PMI it would be a conflict of interest for you to cooperate,because they may uncover information about you during the investigation thatcould cause them to investigate you.
D.Cooperate with PMI by truthfully answering all their questions butrefuse to give them any written documentation.
24.你的一个团队成员,也是一个PMP,正在接受PMP行为规范的违规调查,你应该:
A.完全配合PMI的调查。
B.告诉PMI如果你配合PMI的调查就构成了利益冲突,因为他是你的团队成员。
C.告诉PMI如果你配合PMI的调查就构成了利益冲突,因为他们会透露一些信息从而导致PMI对你的调查。
D.配合PMI的调查,认真回答问题,但拒绝提交任何书面文档。
25.Information-gathering techniques used in the Risk Identificationprocess include all of the following except:
A.Brainstorming
B.Delphi technique
C.Interviewing
D.Monte Carlosimulation
25.风险识别中的信息收集技术包括以下各项,但不包括:
A.头脑风暴
B.德尔菲技术
C.访谈
D.蒙特卡洛

相关试题:

PMP美国项目管理认证模拟预测习题2

PMP考试全真模拟题及答案(样题)

PMP模拟习题汇总(附参考答案)

添加应用,免费套题体验

视频学习

我考网版权与免责声明

① 凡本网注明稿件来源为"原创"的所有文字、图片和音视频稿件,版权均属本网所有。任何媒体、网站或个人转载、链接转贴或以其他方式复制发表时必须注明"稿件来源:我考网",违者本网将依法追究责任;

② 本网部分稿件来源于网络,任何单位或个人认为我考网发布的内容可能涉嫌侵犯其合法权益,应该及时向我考网书面反馈,并提供身份证明、权属证明及详细侵权情况证明,我考网在收到上述法律文件后,将会尽快移除被控侵权内容。

最近更新

社区交流

考试问答