10.You are asked to perform a feasibility study to determine the bestproject to run. Theproject’s initial investment is $29,000. Alternative A’s cash flows are $14,000 for year 1 and $19,000 foryear 2.AlternativeB’s cash inflows are $21,000 for year 1 and $20,000 for year 2. Alternative C’s cash inflows are$15,000 for year 1 and $20,000 for year 2. Assume a 10 percent cost of capital.Which project should you recommend based on the NPV of the threealternatives?
A.Alternative A
B.Alternative B
C.Alternative C
D.None of the above
10.你被要求执行一个可行性分析来决定最佳项目。项目的初始投资为29,000美元。项目A的现金流为第一年14,000美元,第二年为19,000美元,项目B的现金流为第一年21,000美元,第二年为20,000美元,项目C的现金流为第一年15,000美元,第二年为20,000美元。假设资本成本为10%,根据三个项目的净现值,你推荐哪一个项目?
A.项目A
B.项目B
C.项目C
D.哪一个都不推荐
11.All of the following Controlling processes have a change controlsystem as a tool and technique of the process except:
A.Quality Control
B.Scope Change Control
C.Schedule Control
D.Cost Control
11.变更控制系统是下列过程的工具方法,但不包括:
A.质量控制
B.范围变更控制
C.进度控制
D.成本控制
12.This tool and technique of Risk Monitoring and Control is interestedin looking at the implementation and the effective use of the transference,avoidance, and mitigation risk strategies.What is it?
A.Risk reassessment
B.Project change requests
C.Project risk audit
D.Workaround plans
12.这是一个风险监控的工具方法,它被用以查看风险策略中转移、规避和减轻的实施以及有效性,它是什么?
A.风险再评估
B.项目变更请求
C.项目风险审计
D.临时权变计划
13.You and your friend are studying together for the PMP exam. You purchased a copy of this bookto study from while your friend purchased a copy of another author’s book. Both books came with a CD.You each decide to copy the CD fromthe book you purchased to share with each other.Which of the following statements is true?
A.Since neither of you is a PMP yet, you’re not required to adhere tothe PMP Code of Professional Conduct, so sharing the CDs is acceptable.
B.You and your friend should not share the CDs because of conflict ofinterest.
C.The CDs with both books are considered intellectual property andshould not be copied.
D.You and your friend should not share the CDs because of theappearance of impropriety.
13.你和你的朋友一起学习准备PMP考试,你买了一册书,你的朋友买了另一作者的书。这两本书各有一CD,你们决定互相拷贝书上的CD。下面哪一种说法是正确的?
A.因为你们还没有成为PMP,所以不需要遵守PMP行为规范,所以,可以互相拷贝CD。
B.因为存在利益冲突,所为,不能和你的朋友互相拷贝CD。
C.书所附带的CD是知识产权,所以,不能拷贝。
D.因为存在不当行为,所以,不能拷贝。
14.Which of the following choices include all the tools and techniquesto the process of activity duration estimating?
A.Analogous estimating, parametric estimating and three-pointestimating
B.Expert judgment, analogous estimating, parametric estimating andthree-point estimating
C.Expert judgment, analogous estimating, parametric estimatingthree-point estimating durations and reserve analysis
D.Expert judgment, analogous estimating, parametric estimatingthree-point estimating durations and bottom-up estimating
14.活动历时估算的工具方法包括:
A.类比估算、参数估算、三点估算
B.专家判断、类比估算、参数估算、三点估算
C.专家判断、类比估算、参数估算、三点估算和储备分析
D.专家判断、类比估算、参数估算、三点估算和自下而上估算
15.You have received three estimates for your project activity. The optimistic estimate is 245days, the pessimistic estimate is 269 days, and the most likely estimate is 257days. Thisparticular activity is critical to the project, and your project sponsor wantsto know with 95 percent certainty how long it will take to complete thisactivity. Which of thefollowing do you tell the project sponsor?
A.265 days to 273 days
B.253 days to 261 days
C.261 days to 277 days
D.249 days to 265 days
15.你获得项目活动的三种估算。最乐观估算为245天,最悲观估算为269天,最可能估算为257天。这个活动对项目非常关键,你的项目发起人希望获得关于活动历时95%的确定结果,你将向发起人汇报:
A.265至273天
B.253至261天
C.261至277天
D.249至265天
16.The project team closes in on completion when an error is discovered. Fixing the error will actuallycause a change in scope. And if you don’t fix this error, the project deliverable will belate.Which of thefollowing actions do you take?
A.Inform your team to stop working until you can get the CCB toapprove or deny the change.
B.Tell the team to fix the error since this is an emergency and yourauthority is already documented in the procedure.
C.Don't fix the error since there are no procedures documented in yourchange control system for emergencies.
D.Fix the error and inform the CCB at the next meeting because you thinktime is the primary constraint for this project.
16.项目团队快要完工的时候发现一个错误,修复错误将会引起范围的变更;不修复错误,项目交付成果将会延期,你的行动应该是:
A.通知团队停止工作,直到获得CCB批准或者否决这一变更。
B.告诉团队修复错误,因为这是一个紧急事件,而且你的权力已经记录在操作程序里。
C.不要修复错误,因为你的变更控制系统里没有关于紧急状态的程序规定。
D.修复错误,然后下次开会的时候通知CCB,因为你认为时间是该项目的主要约束。
17.You’re working on an internal service project and are in thebeginning of the Planning processes. You noticed that specific staff members were named as project teammembers during your review of the project charter. Which of the following does this question describe?
A.Resource availability
B.Pre-assignment
C.Staff management plan
D.Virtual teams
17.你管理一个内部服务项目并处于计划过程中,你注意到在你审阅项目章程时发现某些员工已经被指定为项目团队成员,这个问题说明了:
A.资源可利用性
B.预分配
C.员工管理计划
D.虚拟团队

相关试题:

PMP美国项目管理认证模拟预测习题2

PMP考试全真模拟题及答案(样题)

PMP模拟习题汇总(附参考答案)

添加应用,免费套题体验

视频学习

我考网版权与免责声明

① 凡本网注明稿件来源为"原创"的所有文字、图片和音视频稿件,版权均属本网所有。任何媒体、网站或个人转载、链接转贴或以其他方式复制发表时必须注明"稿件来源:我考网",违者本网将依法追究责任;

② 本网部分稿件来源于网络,任何单位或个人认为我考网发布的内容可能涉嫌侵犯其合法权益,应该及时向我考网书面反馈,并提供身份证明、权属证明及详细侵权情况证明,我考网在收到上述法律文件后,将会尽快移除被控侵权内容。

最近更新

社区交流

考试问答