PMP美国项目管理认证模拟预测习题2

来源:项目管理师    发布时间:2012-05-07    项目管理师视频    评论

36.Activity A has a duration of 3 days and begins on the morning ofMonday the 4th. Thesuccessor activity B has a finish-to-start relationship with A. The finish-to-start relationshiphas 3 days of lag, and activity B has a duration of 4 days. Sunday is non-workday. What can be determined from thesedata?
A.Calendar time between the start of A to the finish of B is 7
B.Calendar time between the start of A to the finish of B is11
C.Calendar time between the start of A to the finish of B is12
D.Calendar time between the start of A to the finish of B is14
36.活动A的历时为3天,4号星期一上午开始;紧后活动B与活动A是完成开始关系,并有3天的滞后,活动B的历时为4天。星期天为非工作日。根据这些信息,可以判断:
A.活动A的开始到B的完成的日历时间为7天
B.活动A的开始到B的完成的日历时间为11天
C.活动A的开始到B的完成的日历时间为12天
D.活动A的开始到B的完成的日历时间为14天
37.As part of your project plan you must develop an effective method ofcommunication for your multinational team of stakeholders. You have several choices of mediaavailable. What is theappropriate action to take in developing your communication plan?
A.Use the standard media that has been in effect for your previousproject.
B.Use multiple forms of media to ensure that everyone receive theinformation.
C.Discuss the available options with the stakeholder and obtain theirinputs.
D.Obtain additional funding from the project sponsor and develop aproject specific infrastructure.
37.作为项目计划的一部分,你需要为你的项目中的多个国家的干系人制定有效的沟通方法。你有多种沟通媒介可供选择。要制定这样的沟通计划,你应该:
A.利用从前项目中可行的标准媒介
B.利用多种媒介形式,确保每一个人都收到信息
C.与干系人讨论各种选择,获得他们的输入
D.找项目发起人获得额外的资金以便制定针对项目的基础设施
38.You are managing a project to develop nutritional soda for the“under 20” market. You have recently heard that theclient calls your progress reports the “Code of Crap” because they seem to bewritten in a foreign language and incomprehensible.This situation could have beenavoided by.
A.Informing the client at the start of the project of the types ofreports they will receive
B.Using risk management techniques to identify client reports
C.Hiring an expert report writer to prepare standard reports
D.Develop a communication plan
38.你管理一个面向20岁以下市场的营养饮料的开发项目,你最近听说客户把你的进展报告称为“天书”,难以理解。这种情况可以通过什么来避免:
A.在项目开始的时候告诉客户他们将收到的报告类型
B.使用风险管理技巧来识别客户报告
C.雇佣专家来撰写标准报告
D.制定一个沟通计划
39.Investment in project quality improvement is most often borne by the
A.Acquiring organization
B.Project manager
C.Project team
D.Project
39.项目质量改善的投资主要由谁来承担?
A.实施组织
B.项目经理
C.项目团队
D.项目
40.The diagram which ranks defects in order of frequency of occurrence,using a histogram to depict 100 percent of the defects is called:
A.Bar chart
B.Critical path
C.Network chart
D.Pareto chart
40.按照缺陷发生的频率加以排序并用柱状图来描述100%的缺陷,这种方法叫做:
A.横道图
B.关键路径
C.网络图
D.帕雷托图

相关试题:

PMP美国项目管理认证模拟预测习题1

PMP考试全真模拟题及答案(样题)

PMP模拟习题汇总(附参考答案)

添加应用,免费套题体验

上一页345下一页

视频学习

我考网版权与免责声明

① 凡本网注明稿件来源为"原创"的所有文字、图片和音视频稿件,版权均属本网所有。任何媒体、网站或个人转载、链接转贴或以其他方式复制发表时必须注明"稿件来源:我考网",违者本网将依法追究责任;

② 本网部分稿件来源于网络,任何单位或个人认为我考网发布的内容可能涉嫌侵犯其合法权益,应该及时向我考网书面反馈,并提供身份证明、权属证明及详细侵权情况证明,我考网在收到上述法律文件后,将会尽快移除被控侵权内容。

最近更新

社区交流

考试问答