10.A Project Manager wanting an effective meeting will do all of the following except:
A.Produce the meeting agenda
B.Encourage attendees to have their say
C.Communicate the meeting objective
D.Summarize agreements and actions
10.项目经理,如果要召开有效的会议,除了________都需要:
A.准备会议议程
B.鼓励与会者发言
C.传达会议目标
D.总结一致点和行动方案
11.The project payback period is:
A.The time required to pay back all project debts
B.The time required for the company to earn enough to pay for the project
C.The time required post project to reap project benefits equaling project costs
D.The time required from project start to have reaped project benefits equaling the project costs
11.项目的回收期是:
A.偿还所有债务需要的时间
B.公司获得收益足以支付项目所需要的时间
C.项目完工后所获得的项目收益等于项目成本所需要的时间
D.项目开始后所获得的项目收益等于项目投资所需要的时间
12.The following is not true about the Responsibility Matrix:
A.It details people assigned to project roles
B.It details project roles and responsibilities
C.It details when staff are allocated to tasks
D.It is linked to the scope definition or WBS
12.关于职责矩阵,下面哪一个说法是不对的?
A.它详细说明人员的角色分配
B.它详细说明角色和职责
C.它详细说明员工何时分配到任务上
D.它和WBS或者范围定义相关联
13.A Project Manager has ultimate responsibility for the following:
A.Team development
B.Project approval
C.Ensuring no project change once the project is approved
D.Design and test specs
13.项目经理最终负责哪一个?
A.团队发展
B.项目批准
C.项目批准后保证不再变更
D.设计和测试规格
14.The most appropriate time to conduct a project risk assessment is:
A.During scope management planning
B.During risk management planning
C.Just prior to project kick off
D.Whenever a problem is identified
14.进行风险评估的最好时机是:
A.在范围管理规划阶段
B.在风险管理规划阶段
C.在项目开工前
D.问题出现的任何时候
15.You are assessing the cost for a software development project. You discovered that, except for buying CAD application software, you need to hire some staff to plot on it. And more drawings you have, the unit cost will be less. This is because of:
A.Monte Carlo Analysis
B.Cause and Effect
C.Learning Curve Theory
D.The Law of Diminishing Returns
15.你在评估一个软件项目的成本。你发现,除了购买CAD软件费用外,只要雇用人,进行画图,就可以了。这样,你画图越多,单位成本就越低。这是:
A.蒙特卡洛分析
B.因果关系
C.学习曲线理论
D.收益衰减法则
16.There comes a point, a quality level, where spending more money on improving the product or service equals the extra revenue generated by doing so. This is known as:
A.Payback
B.Marginal analysis
C.Product (or service) equilibrium
D.Zero tolerance
16.有一个质量水平点,达到后,用于改善产品或服务的成本刚好等于通过质量改善所产生的收益。这是:
A.回收期
B.边际分析
C.产品平衡
D.零容限
17.Your company has just conducted a bidder's conference. This is a feature of:
A.Procurement planning
B.Solicitation planning
C.Make or Buy analysis
D.Solicitation
17.你的公司刚刚进行了投标人会议,这属于:
A.采购规划
B.询价规划
C.自制外购分析
D.询价
18.Tools and techniques for Information Distribution include all of the following except for:
A.Information gathering and retrieval systems
B.Information distribution methods
C.Project reports and presentations
D.Communications skills and lessons learned process
18.信息发布的工具不包括:
A.信息收集和检索系统
B.信息发布系统
C.项目报告和项目演示
D.沟通技巧和经验教训总结
19.You have received in the proposals for kitting out your new waste treatment plant. All of the following are recommended tools and techniques at this stage except for:
A.A screening system
B.Contract negotiation
C.RFP
D.A weighting system
19.你已经获得了污水处理厂装备项目的建议书,接下来的过程你将使用以下工具方法,但不包括:
A.屏蔽系统
B.合同谈判
C.征集建议书RFP
D.加权系统
20.The following is not true:
A.A project office can be deemed responsible for project results
B.Every project would be better with a project office
C.A project office provides support to the project
D.A project office does not mean a Project Manager is redundant
20.下面哪一种说法不正确:
A.项目办公室也可以对项目结果负责
B.有了一个项目办公室,每一个项目都会更好的
C.项目办公室为项目提供支持
D.有了项目办公室并不是说项目经理就多余了

相关试题:

添加应用,免费套题体验

PMP美国项目管理认证模拟预测习题1

PMP考试全真模拟题及答案(样题)

PMP模拟习题汇总(附参考答案)

视频学习

我考网版权与免责声明

① 凡本网注明稿件来源为"原创"的所有文字、图片和音视频稿件,版权均属本网所有。任何媒体、网站或个人转载、链接转贴或以其他方式复制发表时必须注明"稿件来源:我考网",违者本网将依法追究责任;

② 本网部分稿件来源于网络,任何单位或个人认为我考网发布的内容可能涉嫌侵犯其合法权益,应该及时向我考网书面反馈,并提供身份证明、权属证明及详细侵权情况证明,我考网在收到上述法律文件后,将会尽快移除被控侵权内容。

最近更新

社区交流

考试问答