8. Results of quality control testing and measurement are used
As an input to quality planning
To prepare an operational definition
To prepare a control chart
As an input to quality assurance

质量控制测试与衡量的结果主要用于
作为质量计划编制的一个输入项
为运作定义做准备
为绘制控制图做准备
作为质量保证的一个输入项

9. You are the controller on your project. Your project manager has requested that you provide him with a

forecast of project costs for the next 12months. He needs this information to determine if the budget

should be increased or decreased on this major construction project. In addition to the usual information

sources, which of the following should you also consider?
Cost estimates from similar project
WBS
Project schedule
Existing change requests

你是你们项目的管理员. 你的项目经理要求上报给一个未来12个月的 项目成本的预测报告. 他需要这个信息来判断这个主

建设项目的预算应该啬还是减少. 除了通常的信息资源以外,在下列各项中你还应该考虑哪一项?
类似项目的成本评估
WBS
项目进度时间表
现有的变更要求

10. To use statistical quality control effectively, the project team should know the differences between
Prevention and quality control
Special causes and random causes
Attribute sampling and statistical sampling
Control limits and operational definitions

要有效地使用统计学的质量控制方法,项目团队应该分清哪两个部分的区别
预防与质量控制
特殊性原因与随机性原因
特征抽样与统计抽样
控制限制与运作定义

相关练习题: 

PMP认证考试练习题(十三)(中英文)    

PMP认证考试最新练习题及参考答案汇总

最新试题测试:

每日一练

闯关训练

抢答练习

模拟考场

欢迎进入在线试听:项目管理网上辅导,热招中!!

更多信息请进入:项目管理海量题库  我考网项目管理论坛

上一页12下一页

视频学习

我考网版权与免责声明

① 凡本网注明稿件来源为"原创"的所有文字、图片和音视频稿件,版权均属本网所有。任何媒体、网站或个人转载、链接转贴或以其他方式复制发表时必须注明"稿件来源:我考网",违者本网将依法追究责任;

② 本网部分稿件来源于网络,任何单位或个人认为我考网发布的内容可能涉嫌侵犯其合法权益,应该及时向我考网书面反馈,并提供身份证明、权属证明及详细侵权情况证明,我考网在收到上述法律文件后,将会尽快移除被控侵权内容。

最近更新

社区交流

考试问答