PMP认证考试练习题及参考答案(四十二)

来源:项目管理师    发布时间:2012-05-07    项目管理师视频    评论

1 Japanese resource management models exhibit.
A a cooperative spirit of goal settings
B non-specialized career paths
C frequent changes on team assignments
D A and B.
E All of the above.
ans:E
2 Management by objectives assumes that the team
A is receptive to an unstructured environment.
B does not require close supervision
C possesses a self-fulfillment philosophy
D all of the above 来源:www.examda.com
E A and C
ans:C
3 The performance review interview is a vital component of any personnel evaluation system. Which of the following is not a characteristic of an effective personnel evaluation interview?
A Performed by a supervisor who has adequately prepared for the interview
B Discusses the employee's future performance goals
C Discusses the employee's undesirable personality traits
D Completed during a single, uninterrupted block of time
E Focuses on a limited number of topics so that each topic can be discussed in detail
ans:C
4 Management by Objectives (MBO)
A is a method used to evaluate personnel by objectively comparing them to common performance standards
B requires a supervisor and a subordinate to jointly establish performance objectives
C should be the responsibility of the organization's personnel department
D should always involve the establishment of objectives that are quantifiable
E B and D
ans:B
5 According to labor law, which of the following management actions are prohibited during a union organizing drive?
A Forbidding employees from distributing union literature in working areas
B Implementing previously scheduled pay raises
C Forbidding unions from soliciting workers during working hours
D Circulating anti-union petitions http://ks.examda.com
E All of the above
ans:D
6 Filling vacant positions by recruiting within the organization
A Is exempt from equal employment opportunity laws
B Is less expensive than recruiting externally
C Can help provide new and innovative ideas to the organization
D Is more time consuming than recruiting externally
E A and B
ans:B
7 Flextime and compressed workweeks are two popular alternative work schedules used by employers to improve the quality of work life of their employers. Which of the following statements concerning these alternative work schedules is not true?
A Flextime schedules alter the employee's working hours but not the number of hours worked each day
B Both flextime and compressed workweek schedules make scheduling more complex for the employer
C Both flextime and compressed workweek schedules can complicate compliance with overtime regulations
D Fatigue is a disadvantage of compressed workweek schedules because employees must work longer than the traditional eight hour work day
E Under flextime schedules, the working hours are established by the employer
ans:E
8 Forecasting human resource requirements necessitates making predictions about both the supply and demand of human resources. Which of the following is not a method used to forecast the demand for human resources?
A Delphi Method
B Regression Analysis
C PERT Charts
D Staffing Tables
E Time Series Analysis
ans:C
9 Which of the following statements is in agreement with McGregor's concepts concerning Theory X and Theory Y managers?
A Theory X managers view subordinates as being lazy, irresponsible, and resistant to change
B Theory Y managers view subordinates as being imaginative, creative, and willing to accept responsibility
C Theory X managers tend to be autocratic whereas Theory Y managers are more likely to delegate responsibility
D A and B.
E All of the above
ans:E
10 The project team form of organization confers both advantages and disadvantages. Disadvantages of the project form include:
A Conflict in authority between project manager and functional managers
B Dual allegiance on part of team members 来源:www.examda.com
C Complex prioritization of resources
D Loss of developed procedures on project dissolution
E All of the above
ans:E
11 In general, groups will ____ the average individual problem solver on problems with multiple stages.
A Perform better than
B Perform worse than
C Take less time than
D Do about as well as 
ans:A
12 Which of the following would most likely not be an essential objective of a project team kick-off meeting
A Create a project technology master plan
B Get team members to know one another
C Identify project problem areas
D Obtain individual and group commitments
E Identify the project coordinator
ans:A

上一页12下一页

视频学习

我考网版权与免责声明

① 凡本网注明稿件来源为"原创"的所有文字、图片和音视频稿件,版权均属本网所有。任何媒体、网站或个人转载、链接转贴或以其他方式复制发表时必须注明"稿件来源:我考网",违者本网将依法追究责任;

② 本网部分稿件来源于网络,任何单位或个人认为我考网发布的内容可能涉嫌侵犯其合法权益,应该及时向我考网书面反馈,并提供身份证明、权属证明及详细侵权情况证明,我考网在收到上述法律文件后,将会尽快移除被控侵权内容。

最近更新

社区交流

考试问答