13 Perhaps the biggest problem facing the project manager during integration activities within a matrix structure is:
A Coping with employees who report to multiple bosses
B Too much sponsorship involvement
C Unclear functional understanding of the technical requirements
D Escalating project costs
E All of the above
ans:A
14 The project manager has, as a prime responsibility, to assure proper integration of activities. In which organizational form does the project manager probably have the easiest time in integrating work?
A Matrix
B Classical
C Expediter
D Coordinator 来源:考
E Pure project
ans:E
15 The traditional organizational form has the disadvantage of:
A Complex functional budgeting
B Poorly established communication channels
C No single focal point for clients/sponsors
D Slow reaction capability
E Inflexible use of manpower
ans:C
16 Douglas McGregor's Theory Y advocates that the average worker:
A Dislikes work and avoids it whenever possible
B Must be closely supervised and even threatened with punishment
C Avoids increased responsibility
D Wants self-respect
E None of the above
ans:D
17 Universal characteristics of effective project managers include such skills as communication, decision-making, planning, ability to identify problems and:
A Performing feasibility studies
B Proposal preparation
C being close to the customer
D Maturity
E None of the above are universal characteristics
ans:E
18 The project manager must be concerned with building a closely knit team. During the project kickoff meeting, the project manager can get a good start at team building by providing the team with:
A Proposed salary increases if the project is successful
B Bonuses for early completion date
C A promise of future assignments
D Well-defined project objectives
E Linear responsibility charts
ans:D
19 A common way by which executives provide the project manager with written authority is through:
A A common job description for all project managers
B An appointment letter 我考网论坛
C A project charter
D All of the above
E B and C only
ans:E
20 Which of the following time robbers end up creating additional work for the project manager and the project office?
A Failure to delegate
B Changes without notification or direction
C Unreasonable time constraints
D Over directing people
E All of the above
ans:E

相关练习题: 

PMP认证考试练习题及参考答案(四十四) 

PMP认证考试最新练习题及参考答案汇总

精品推荐:

PMP全真试题精选

欢迎进入在线试听:项目管理网上辅导,热招中!!

更多信息请进入:项目管理海量题库  我考网项目管理论坛

上一页12下一页

视频学习

我考网版权与免责声明

① 凡本网注明稿件来源为"原创"的所有文字、图片和音视频稿件,版权均属本网所有。任何媒体、网站或个人转载、链接转贴或以其他方式复制发表时必须注明"稿件来源:我考网",违者本网将依法追究责任;

② 本网部分稿件来源于网络,任何单位或个人认为我考网发布的内容可能涉嫌侵犯其合法权益,应该及时向我考网书面反馈,并提供身份证明、权属证明及详细侵权情况证明,我考网在收到上述法律文件后,将会尽快移除被控侵权内容。

最近更新

社区交流

考试问答