13 A scientist is informing techs. about a new product which is starting and the type of work that the lab techs. will be expected to do. The barriers which could hinder the lab techs. ability to filter the information include all of the following except:
A language and semantics
B culture and ethics
C intelligence and knowledge base
D reputation, authority, organizational status and position
E relative location of the lab to the scientist's office
ans:E
14 A project manager can exchange information with the project team using which media?
A tactile
B audio
C olfactory
D visual 我考网(www.Examda。com)
E All of the above.
ans:E
15 Things that distort, distract, or muddle the communication process are called:
A noise
B selective filtering
C selective perception
D medium problems
E All of the above.
ans:A
16 Project managers must know:
A What kind of message to send
B to whom to send the message
C how to translate the message into a language that everyone can understand
D All of the above
E A and B only
ans:D
17 Communication management is best described as conducting or supervising
A the way we listen
B the way we speak
C the way we feel
D the exchange of information
E perfect documentation activities
ans:D
18 To determine whether or not the employee correctly understands the message, the project manager needs to:
A reduce the filtering
B eliminate barriers
C obtain feedback
D use more than one medium
E use all of the above.
ans:C
19 Surveys have shown that the primary skill needed to be a project manager is communication skill. The typical project manager spends approximately ______percent of his or her time communicating.
A 40-50
B 50-60
C 60-75 来源:考
D 75-90
E 90-95
ans:D
20 You are giving your team instructions on how to perform a new test which is different from the way that the team had performed it previously. The best way to verify that the learn understands what you want is to:
A obtain feedback
B analyze the team's perceptions barriers
C uses gestures in presenting the instructions
D analyze the team's decoding skills
E analyze the team's encoding skills
ans:A

相关练习题: 

PMP认证考试练习题及参考答案(四十九) 

PMP认证考试最新练习题及参考答案汇总

精品推荐:

PMP全真试题精选

欢迎进入在线试听:项目管理网上辅导,热招中!!

更多信息请进入:项目管理海量题库  我考网项目管理论坛

上一页12下一页

视频学习

我考网版权与免责声明

① 凡本网注明稿件来源为"原创"的所有文字、图片和音视频稿件,版权均属本网所有。任何媒体、网站或个人转载、链接转贴或以其他方式复制发表时必须注明"稿件来源:我考网",违者本网将依法追究责任;

② 本网部分稿件来源于网络,任何单位或个人认为我考网发布的内容可能涉嫌侵犯其合法权益,应该及时向我考网书面反馈,并提供身份证明、权属证明及详细侵权情况证明,我考网在收到上述法律文件后,将会尽快移除被控侵权内容。

最近更新

社区交流

考试问答