1 Selective perception is _____ of new conflicting information that may result, in a breakdown in communication.
A Encoding
B Blocking out
C Transmission
D Acceptance
E Decoding
ans:B
2 Project managers that are available to answer questions, provide guidance when need, and generally do not interfere with day-to-day activities have a(n) ______ managerial style.
A Autocratic
B Conciliatory
C Ethical
D Facilitative
E Judicial 来源:我考网网
ans:D
3 Most project (and non-project) managers prefer _____ communications.
A Oral
B Written
C Upward
D Downward
E Lateral
ans:A
4 Management calls a meeting to explain to all employees the new benefits package for the rank and file. This is an example of:
A Upward communication
B Downward communication
C One-way communication
D Two-way communication
E None of the above.
ans:C
5 The project manager must receive reports and briefings from engineers, contracting officers, procurement personnel and marketing people. The project manager's communication dilemma is one of:
A encoding
B decoding
C choice of a medium
D one-way communication
E All of the above.
ans:E
6 The way a project manager sends and receives information depends upon:
A How others relate to the project manager
B The project manager's level in the organizational hierarchy
C the size and nature of the project
D the project manager's salary and age 来源:www.examda.com
E the number of projects going on at one time in the company
ans:A
7 Adding 5 people to a 4 person team increases the communication channels by a factor of:
A 2 times
B 3 times
C 4 times
D 5 times
E 6 times
ans:E
8 Which of the following is often overlooked in achieving effective communication?
A speaking clearly
B listening
C interpreting
D maintaining eye contact
E manipulating the conversation
ans:B
9 The basic elements of communication include:
A Listening, talking and sign language.
B Communicator, encoding, message, medium, decoding, receiver, and feedback
C Clarity of speech and good listening habits
D Reading, writing and listening
E All of the above
ans:B
10 Communications is best described as:
A an exchange of information.
B providing written or oral directions.
C consists of senders and receivers 来源:考
D effective listening.
E All of the above
ans:E
11 The purpose of project Risk Management is to:
A Identify those factors that will adversely impact project objectives.
B Assess the impact of adverse project factors.
C Assess the probability of adverse project factors.
D A and C
E All of the above.
ans:E
12 Project Risk Management is based on which of the following premises:
A the future is unknown.
B unknowns can result in risks or opportunities.
C we cannot control risk events.
D project risk impact can be measured and controlled
E All of the above.
ans:E

上一页12下一页

视频学习

我考网版权与免责声明

① 凡本网注明稿件来源为"原创"的所有文字、图片和音视频稿件,版权均属本网所有。任何媒体、网站或个人转载、链接转贴或以其他方式复制发表时必须注明"稿件来源:我考网",违者本网将依法追究责任;

② 本网部分稿件来源于网络,任何单位或个人认为我考网发布的内容可能涉嫌侵犯其合法权益,应该及时向我考网书面反馈,并提供身份证明、权属证明及详细侵权情况证明,我考网在收到上述法律文件后,将会尽快移除被控侵权内容。

最近更新

社区交流

考试问答