  Develop Project Management Plan
  制定项目管理计划
  The Develop Project Management Plan process includes the actions necessary to define,integrate,and coordinate all subsidiary plans into a project management plan.The project management plan content will vary depending upon the application area and complexity of the project.This process results in a project management plan that is updated and revised through the Integrated Change Control process.The project management plan defines how the project is executed,monitored and controlled,and closed.The project management plan documents the collection of outputs of the planning processes of the Planning Process Group and includes:
  制定项目管理计划过程包括将确定、协调与综合所有部分计划所需要的行动形成文件,使其成为项目管理计划。项目管理计划的内容因项目的应用领域和复杂程度而异。这一过程的结果使项目管理计划通过整体变更控制过程得以更新与修改。项目管理计划确定了执行、监视、控制和结束项目的方式与方法。项目管理计划记录了规划过程组的各个规划子过程的全部成果,其中有:
  The project management processes selected by the project management team
  项目管理团队选择的各个项目管理过程。
  The level of implementation of each selected process
  每一选定过程的实施水平。
  The descriptions of the tools and techniques to be used for accomplishing those processes
  对实施这些过程时使用的工具与技术所做的说明。
  How the selected processes will be used to manage the specific project,including the dependencies and interactions among those processes,and the essential inputs and outputs
  在管理具体项目中使用选定过程的方式和方法,包括过程之间的依赖关系和相互作用,以及重要的依据和成果。
  How work will be executed to accomplish the project objectives
  为了实现项目目标所执行工作的方式、方法。
  How changes will be monitored and controlled
  监控变更的方式、方法。
  How configuration management will be performed
  实施配置管理的方式、方法。
  How integrity of the performance measurement baselines will be maintained and used
  使用实施效果测量基准并使之保持完整的方式、方法。
  The need and techniques for communication among stakeholders
  利害关系者之间的沟通需要与技术。
  The selected project life cycle and,for multi-phase projects,the associated project phases
  选定的项目生命期和多阶段项目的项目阶段。
  Key management reviews for content,extent,and timing to facilitate addressing open issues and pending decisions.
  高层管理人员为了加快解决未解决的问题和处理未做出的决策,对内容、范围和时间安排的关键审查。
  The project management plan can be either summary level or detailed,and can be composed of one or more subsidiary plans and other components.Each of the subsidiary plans and components is detailed to the extent required by the specific project.These subsidiary plans include,but are not limited to:
  项目管理计划详略均可,可由一个或多个部分计划,以及其他事项组成。每一个分计划和其他组成部分的详细程度都要满足具体项目的需要。这些分计划包括但不限于如下内容:
  Project scope management plan
  项目范围管理计划
  Schedule management plan
  进度管理计划
  Cost management plan
  费用管理计划
  Quality management plan
  质量管理计划
  Process improvement plan
  过程改进计划
  Staffing management plan
  人员配备管理计划
  Communication management plan
  沟通管理计划
  Risk management plan
  风险管理计划
  Procurement management plan
  采购管理计划
  These other components include,but are not limited to:
  其他组成部分包括,但不限于如下事项:
  Milestone list
  里程碑清单
  Resource calendar
  资源日历
  Schedule baseline
  进度基准
  Cost baseline
  费用基准
  Quality baseline
  质量基准
  Risk register
  风险登记册

视频学习

我考网版权与免责声明

① 凡本网注明稿件来源为"原创"的所有文字、图片和音视频稿件,版权均属本网所有。任何媒体、网站或个人转载、链接转贴或以其他方式复制发表时必须注明"稿件来源:我考网",违者本网将依法追究责任;

② 本网部分稿件来源于网络,任何单位或个人认为我考网发布的内容可能涉嫌侵犯其合法权益,应该及时向我考网书面反馈,并提供身份证明、权属证明及详细侵权情况证明,我考网在收到上述法律文件后,将会尽快移除被控侵权内容。

最近更新

社区交流

考试问答