2005年下半年信息系统项目管理师考试上午试题

来源:软件水平考试    发布时间:2012-11-04    软件水平考试视频    评论



  ● 在ISO OSI/RM中,__(61)__实现数据压缩功能。
  (61)A.应用层     B.表示层    C.会话层   D.网络层

  ● 以下连网设备中,工作于网络层的设备是__(62)__。
  (62)A.调制解调器   B.以太网交换机 C.集线器   D.路由器

  ● 100BaseFX采用的传输介质是__(63)__。
  (63)A.双绞线    B.光纤      C.无线电波  D.同轴电缆

  ● 在下列网络服务中,__(64)__是远程登录服务,Internet中域名与IP地址之间的翻译是由__(65)__来完成的。
  (64)A.WWW      B.FTP       C.BBS     D.Telnet
  (65)A.域名服务器  B.代理服务器   C.FTP服务器  D. Web服务器

  ● __(66)__ means that every project has a definite beginning and a definite end.
  (66)A. Project phase B. Unique    C. Temporary   D. Closure

  ● The __(67)__ defines the phases that connect the beginning of a project to its end.
  (67)A. schedule  B. project life cycle C. temporary D. milestone

  ● __(68)__ are individuals and organizations that are actively involved in the project, or whose interests may be affected as a result of project execution or project completion.
  (68)A. Project managers    B. Project team members
     C. Sponsors        D. Project stakeholders

  ● The __(69)__ Process Group consists of the processes used to complete the work defined in the project management plan to accomplish the project's requirements.
  (69)A. Planning B. Executing  C. Monitoring and Controlling D. Closing

  ● The __(70)__ provides the project manager with the authority to apply organizational resources to project activities.
  (70)A. project management plan   B. contract
     C. project human resource plan D. project charter

  ● The __(71)__ describes, in detail, the project's deliverables and the work required to create those deliverables.
  (71)A. project scope statement   B. project requirement
     C. project charter       D. product specification

  ● The process of __(72)__ schedule activity durations uses information on schedule activity scope ofwork, required resourcetypes,estimated resource quantities, and resource calendars with resource availabilities.
  (72)A. estimating  B. defining  C. planning  D. sequencing

  ● PDM includes four types of dependencies or precedence relationships: ... __(73)__. The completion of the successor activity depends upon the initiation of the predecessor activity.
  (73)A. Finish-to-Start    B. Finish-to-Finish
     C. Start-to-Start     D. Start-to-Finish

  ● __(74)__ is the budgeted amount for the work actually completed on the schedule activity or WBS component during a giving time period.
  (74)A. Planned value B. Earned value C. Actual cost D. Cost variance

  ● __(75)__ involves comparing actual or planned project practices to those of other projects to generate ideas for improvement and to provide a basis by which to measure performance. These other projects can be within the performing organization or outside of it, and can be within the same or in another application area.
  (75)A. Metrics  B. Measurement  C. Benchmarking  D. Baseline

上一页567下一页

视频学习

我考网版权与免责声明

① 凡本网注明稿件来源为"原创"的所有文字、图片和音视频稿件,版权均属本网所有。任何媒体、网站或个人转载、链接转贴或以其他方式复制发表时必须注明"稿件来源:我考网",违者本网将依法追究责任;

② 本网部分稿件来源于网络,任何单位或个人认为我考网发布的内容可能涉嫌侵犯其合法权益,应该及时向我考网书面反馈,并提供身份证明、权属证明及详细侵权情况证明,我考网在收到上述法律文件后,将会尽快移除被控侵权内容。

最近更新

社区交流

考试问答