8. Using a backward pass, if the duration of Task F is reduced to 12 days, what are the LS (late start) and LF (late finish) for Task E?
LS=15, LF=20
LS=16, LF=21
LS=17, LF=22
LS=14, LF=19

使用反推法,如果任务F的工期减少到12天,对于任务F最迟开始和最迟完成的日期是多少?
LS=15, LF=20
LS=16, LF=21
LS=17, LF=22
LS=14, LF=19

9. The ES date for task “h” in the above project is 9/5 and the EF date for the task 9/10.the PM finds that task “g” will start on time but will take eight days longer than anticipated. If nothing else has changed, how will this affect the project?
The project will finish eight days late.
The finish date will remain the same
The critical path will change.
Task “g” becomes part of the critical path.

对任务“H”的最早开始日期是9/5同时任务的最早完成日期是9/10. 项目经理发现任务“G”准时开始但比预期要长8天完成. 如果没有其他变化,它将对项目产生什么影响?
项目迟8天完成
项目准时完成
关键路径将改变
任务“G”变成关键路径的一部分

10. Due to a lack of employee training and proper production controls, defects in a production run caused rework which cost the company $250,000. How much of this cost is directly attributable to the employees on the production line?
$75,000
$37,500
$145,000
$150,000

由于缺乏雇员培训和适当的产品控制,缺陷在产品中存在导致重做,它花费了$250,000. 生产线的员工应负多少成本损失的责任?
$75,000
$37,500
$145,000
$150,000

相关练习题: 

PMP认证考试练习题(十)(中英文)    

PMP认证考试最新练习题及参考答案汇总

最新试题测试:

每日一练

闯关训练

抢答练习

模拟考场

欢迎进入在线试听:项目管理网上辅导,热招中!!

更多信息请进入:项目管理海量题库  我考网项目管理论坛

上一页12下一页

视频学习

我考网版权与免责声明

① 凡本网注明稿件来源为"原创"的所有文字、图片和音视频稿件,版权均属本网所有。任何媒体、网站或个人转载、链接转贴或以其他方式复制发表时必须注明"稿件来源:我考网",违者本网将依法追究责任;

② 本网部分稿件来源于网络,任何单位或个人认为我考网发布的内容可能涉嫌侵犯其合法权益,应该及时向我考网书面反馈,并提供身份证明、权属证明及详细侵权情况证明,我考网在收到上述法律文件后,将会尽快移除被控侵权内容。

最近更新

社区交流

考试问答