PMP认证考试练习题(十三)(中英文)

来源:项目管理师    发布时间:2012-05-07    项目管理师视频    评论

8. You have prepared the scope statement and the WBS for your project plan. Your project is now under way, but you recognize that, given the nature of project work, scope change is inevitable. You also are aware of the danger of scope creep, having suffered the consequences of it recently. To avoid a similar experience, you meet with your team and decide to establish a project scope change control system. This is-
A collection of formal, documented procedures to define the steps by which official project documents may be changed
A documented process used to apply technical and administrative direction and surveillance to identify and document functional and physical characteristics of items, record and report change, control change, and audit the items and system to verify conformance to requirements
A set of procedures by which project scope may be changed, including the paperwork, tracking systems, and approval levels necessary for authorizing change
Mandatory for use on project so that the scope management plan cannot be changed without prior review and sign-off

你已经准备好了项目的范围说明和WBS, 你的项目计也已经被准备了. 目前你的项目开始实施了,但你认识到,基于项目工作的天性,项目范围的变动是在所难免的. 由于不久前你就经历过范围不断扩大的折磨,所以这次你对范围蔓延的危险特别留意. 为了避免类似事件的发生,你召集了团队会议要建立一套项目范围变更控制系统. 这是指
一系列正式的有证明文件的程序来规定改变正式的项目文件的步骤
一套有证明文件的流程,用其来实施技术和行政的指导和监督以明确和说明项目的 功能与物理特征,记录并报告变化的发生,控制变化并对项目和系统进行检验其与要求的一致性
可以使项目范围得到变更的一系统程序,主要包括文书工作、跟踪系统和批准变更 必须的审批级别
针对项目的命令保证项目的范围管理计划在签署之前不会被随意改变

9. When managing current projects, it is important to use lessons learned from previous projects to improve the organization’s project management process. Therefore, in project closing procedures, it is important to review the-
Secondary risks that occurred
Checklists for risk identification
WBS dictionary
Team members’ curriculum vitae

在管理当前项目的时候,运用从以往项目中吸取的经验教训来改善公司项目管理的流程是非常重要的. 因此,在项目收尾程序中,回顾下列哪项是比较重要的
曾发生过的中等风险
风险鉴别对照单
WBS计划书
团队成员简历

10. You are working to close out your project. During these hectic final days of the project, most conflict arises from-
Schedule problems
Cost overruns
Technical problems
Lack of customer acceptance

你目前正在从事项目的收尾工作. 在这个令人兴奋的最后阶段,在下列哪个方面最容易引发冲突
进度问题
成本超支
技术问题
缺乏客户的认同

相关练习题: 

PMP认证考试练习题(十四)(中英文)    

PMP认证考试最新练习题及参考答案汇总

最新试题测试:

每日一练

闯关训练

抢答练习

模拟考场

欢迎进入在线试听:项目管理网上辅导,热招中!!

更多信息请进入:项目管理海量题库  我考网项目管理论坛

上一页12下一页

视频学习

我考网版权与免责声明

① 凡本网注明稿件来源为"原创"的所有文字、图片和音视频稿件,版权均属本网所有。任何媒体、网站或个人转载、链接转贴或以其他方式复制发表时必须注明"稿件来源:我考网",违者本网将依法追究责任;

② 本网部分稿件来源于网络,任何单位或个人认为我考网发布的内容可能涉嫌侵犯其合法权益,应该及时向我考网书面反馈,并提供身份证明、权属证明及详细侵权情况证明,我考网在收到上述法律文件后,将会尽快移除被控侵权内容。

最近更新

社区交流

考试问答