8. A project manager believes that modifying the scope of the project may provide added value for the customer. The project manager should:
Change the scope baseline
Prepare a variance report
Call a meeting of the change control board
Postpone the modification until a separate enhancement project is funded after this
project is completed according to the original baseline.

某项目经理相信: 调整项目的范围可能为客户提供附加价值. 该项目经理应该:
变更范围基准计划
准备一份偏差报告
召集变更控制委员会的开会
依照最初的基准计划完成项目后, 为另一个改进的项目筹得了资金, 再进行调整

9. Using the figure below, what is the probability that project1 will be selected and completed successfully?
50%
30%
60%
40%

用下面数字计算, 项目1将会被选择并且成功完成的概率是多少?
a. 50%
b. 30%
c. 60%
d. 40%

10. The requirements and functional specifications have been completed and the acceptance test strategy is now in development. At what point in the project should the project manager plan for events not happening in accordance with the project plan?
When the unanticipated events occur, because this approach saves you valuable time
Contingency planning should occur throughout the project life cycle
Only during the development of the risk management plan
Contingency planning occurs mainly in the Design Phase

已经完成了需求和功能规格的制定,正在制定验收测试策略. 在项目的什么阶段时刻, 项目经理应该安排处理哪些与项目计划预计发生偏差的事件?
a. 当未预料到的事件发生的时候,由于这种方法节省你宝贵的时间
b. 意外事件规划应该贯穿于整个项目生命周期
c. 仅在风险管理计划制定期间
d. 意外事件规划主要地在项目设计阶段进行

相关练习题: 

PMP认证考试练习题(十八)(中英文)    

PMP认证考试最新练习题及参考答案汇总

最新试题测试:

每日一练

闯关训练

抢答练习

模拟考场

欢迎进入在线试听:项目管理网上辅导,热招中!!

经验交流请访问:

我考网项目管理论坛,一起互动起来吧!

上一页12下一页

视频学习

我考网版权与免责声明

① 凡本网注明稿件来源为"原创"的所有文字、图片和音视频稿件,版权均属本网所有。任何媒体、网站或个人转载、链接转贴或以其他方式复制发表时必须注明"稿件来源:我考网",违者本网将依法追究责任;

② 本网部分稿件来源于网络,任何单位或个人认为我考网发布的内容可能涉嫌侵犯其合法权益,应该及时向我考网书面反馈,并提供身份证明、权属证明及详细侵权情况证明,我考网在收到上述法律文件后,将会尽快移除被控侵权内容。

最近更新

社区交流

考试问答