PMP认证考试练习题(十九)(中英文)

来源:项目管理师    发布时间:2012-05-07    项目管理师视频    评论

8. Using the figure below, activity L has an early start time of weeks and an early finish time of weeks.
11, 13
12, 14
13, 15
15, 17

PMP认证考试练习题(十九)(中英文)

利用下图所示数字计算,活动 L有最早开始时间 周和最早完成时间 周.
11,13
12,14
13,15
15,17

PMP认证考试练习题(十九)(中英文)

9. Core planning processes have clear dependencies that require them to be performed in essentially the same order on most projects. Which of the following is the correct order as a portion of core planning processes?
Scope planning, scope definition, activity sequencing, activity duration estimation
Scope definition, scope planning, activity definition, activity sequencing, activity duration estimation
Scope planning, scope definition, activity sequencing, activity definition, activity duration estimation
Activity duration estimation, scope planning, scope definition, activity definition, activity sequencing

核心计划过程有明确的依赖关系,在大多数项目中要以同样的顺序必须完成. 下列哪一项符合核心计划过程的正确顺序:.
a. 范围规划--范围定义--活动排序--活动工期估计
b. 范围定义--范围规划--活动定义--活动排序--活动工期估计
c. 范围规划--范围定义--活动排序--活动定义--活动工期估计
d. 活动工期估计--范围规划--范围定义--活动定义--活动排序

10.In which project life cycle phase is uncertainty associated with project integration usually the greatest?
Project executing
Project planning
Project closeout
Project approval

在项目生命周期哪一阶段,项目整合的不确定性最大?
a. 项目执行
b. 项目规划
c. 项目收尾
d. 项目审定

相关练习题: 

PMP认证考试练习题(二十)(中英文)    

PMP认证考试最新练习题及参考答案汇总

最新试题测试:

每日一练

闯关训练

抢答练习

模拟考场

欢迎进入在线试听:项目管理网上辅导,热招中!!

经验交流请访问:

我考网项目管理论坛,一起互动起来吧!

上一页12下一页

视频学习

我考网版权与免责声明

① 凡本网注明稿件来源为"原创"的所有文字、图片和音视频稿件,版权均属本网所有。任何媒体、网站或个人转载、链接转贴或以其他方式复制发表时必须注明"稿件来源:我考网",违者本网将依法追究责任;

② 本网部分稿件来源于网络,任何单位或个人认为我考网发布的内容可能涉嫌侵犯其合法权益,应该及时向我考网书面反馈,并提供身份证明、权属证明及详细侵权情况证明,我考网在收到上述法律文件后,将会尽快移除被控侵权内容。

最近更新

社区交流

考试问答