8. Debra realizes she must determine the aspects of her project that may be at risk. Which of following is not a useful tool for her to use in identifying these risks?
Ishikawa diagrams
System or process flowcharts
Interviews with stakeholders
Corrective action

Debra 认识到她必须决定项目可能在哪些方面有风险. 在识别这些风险中,下列哪一工具对她没有什么用处?
Ishikawa 图
系统或方式流程表
与项目相关者面谈
纠正行动

9. Using the table below, the expected profit (or loss) of using the aggressive schedule is:
($ 25,000)
$ 75,000
$ 78,000
$ 100,000

PMP认证考试练习题(二十一)(中英文)

用下表数据计算,用积极的进度的预期的利润 ( 或损失) 是:
($25,000)
$75,000
$78,000
$100,000

PMP认证考试练习题(二十一)(中英文)

10. An organization is considering bidding on a project in a new technology area with which it has no prior experience. The organization was able to locate knowledgeable experts in that field to help understand the new aspects. Therefore, probabilities can be assigned to possible profit or loss outcomes of this project. This would be an example of decision making under:
Certainty
Risk
Uncertainty
Pure risk

一个组织在考虑竞标一个新技术领域的项目,但对该技术领域没有经验,组织能识别找出该领域知识专家来帮助理解这个新的领域. 因此,能够确定该项目可能的利润或损失结果概率. 这会是一个在什么条件下的决策例子:
确定性
风险
不确定性
纯粹的风险

相关练习题: 

PMP认证考试练习题(二十二)(中英文)    

PMP认证考试最新练习题及参考答案汇总

最新试题测试:

每日一练

闯关训练

抢答练习

模拟考场

欢迎进入在线试听:项目管理网上辅导,热招中!!

经验交流请访问:

我考网项目管理论坛,一起互动起来吧!

上一页12下一页

视频学习

我考网版权与免责声明

① 凡本网注明稿件来源为"原创"的所有文字、图片和音视频稿件,版权均属本网所有。任何媒体、网站或个人转载、链接转贴或以其他方式复制发表时必须注明"稿件来源:我考网",违者本网将依法追究责任;

② 本网部分稿件来源于网络,任何单位或个人认为我考网发布的内容可能涉嫌侵犯其合法权益,应该及时向我考网书面反馈,并提供身份证明、权属证明及详细侵权情况证明,我考网在收到上述法律文件后,将会尽快移除被控侵权内容。

最近更新

社区交流

考试问答