8. A person estimates that a commute will most likely take I hour. On further questioning, she estimates that the trip could take as little as 45 minutes, best case, or as long as I hour 45minutes, worst case, what is the standard deviation based on the estimates?
A. 10 minutes
B. 15minutes
C. 50 minutes
D. 60 minutes

8. 一个人估计她回家最可能的情况是花1小时间。她又进一步推算,在最快情况下要45分钟,最慢要1小时45分钟。基于这样的估计,这个人回家所花的时间的标准差是多少
A. 10分钟
B. 15分钟
C. 50分钟
D. 60分钟

9. Projects are particularly susceptible to risk because
A. Murphy’s law stated that “if something can go wrong, it will’”
B. Each project is unique in some measure
C. Project management tools are generally unavailable at the project team level
D. There are never enough resources to do the job
9. 由于以下哪个原因,项目特别容易受到风险的影响:
A. 墨菲定律表明:“如果可能会生问题,问题将会出现”
B. 每个项目在某些方面是独特的
C. 项目管理工具对于项目小组是不可得的
D. 完成工作的资源永远是不足的

答案:B
项目的特征-独特的产品、服务或成果:
关于项目的特征——独特性”

10. What doctrine causes a party to relinquish rights under a contract because it knowingly fails to execute those rights?
A. Assignment of claims
B. Matebal breach
C. Waiver
D. Warranties
10. 根据什么理论,使得当事一方由于有意不实施合同权利而放弃一个合同下的权利?
A. 权利转让
B. 严重违约
C. 自动弃权
D. 授权

相关练习题:   

PMP认证考试最新练习题及参考答案汇总

最新试题测试:

每日一练

闯关训练

抢答练习

模拟考场

欢迎进入在线试听:项目管理网上辅导,热招中!!

经验交流请访问:

我考网项目管理论坛,一起互动起来吧!

上一页12下一页

视频学习

我考网版权与免责声明

① 凡本网注明稿件来源为"原创"的所有文字、图片和音视频稿件,版权均属本网所有。任何媒体、网站或个人转载、链接转贴或以其他方式复制发表时必须注明"稿件来源:我考网",违者本网将依法追究责任;

② 本网部分稿件来源于网络,任何单位或个人认为我考网发布的内容可能涉嫌侵犯其合法权益,应该及时向我考网书面反馈,并提供身份证明、权属证明及详细侵权情况证明,我考网在收到上述法律文件后,将会尽快移除被控侵权内容。

最近更新

社区交流

考试问答