13 It is useful to conduct project risk assessment according to the project's
A charter
B statement of work
C Work Breakdown structure
D network
E budget
ans:C
14 Uncertainty refers to a situation where:
A the outcomes are known but their probabilities are high
B the outcomes and their probabilities are known
C neither the outcomes nor their probabilities are known
D states of nature can change at any time
E probabilities of various states of nature can change at any time
ans:C
15 The lowest dollar amount 'at stake' is associated with the following phase of the project:
A conceptual
B execution
C cut-over
D post project evaluation
E A and D only
ans:A
16 The highest degrees of project risk and uncertainty are associated with the following phase of the project:
A conceptual
B execution 我考网论坛
C cut-over
D post project evaluation
E A and D only
ans:A
17 Risk management allows the project manager and the project team to:
A eliminate most risks during the planning phase of the project
B identify project risks
C identify impacts of various risks
D plan suitable responses
E B, C and D only
ans:E
18 Since risk is associated with most projects, the best course of action is to:
A cover all project risks by buying appropriate insurance
B ignore the risks, since nothing can be done about them and move forward with the project in an expeditious manner.
C avoid projects with clear and present risks
D eliminate all known risks prior to the execution phase of the project
E identify various risks and implement actions to mitigate their potential impact
ans:E
19 When items to be purchased for a project are specified by performance characteristics:
A paperwork is greatly reduced
B the supplier is held liable for the operation of the item
C the supplier is held liable for the maintenance of the item
D the supplier is held liable for that the item meets the design, dimensions, and tolerance specifications.
E B and D only
ans:B
20 Which of the following is a formal invitation that requests a formal response that describes the method of work and associated compensation.
A Request for quotation (RFQ)
B Request for proposal (RFP) 来源:考
C Request for bids (RFB)
D Invitation for bids (IFB)
E Letter of intent (LOI)
ans:B

相关练习题: 

PMP认证考试练习题及参考答案(五十四) 

PMP认证考试最新练习题及参考答案汇总

精品推荐:

PMP全真试题精选

欢迎进入在线试听:项目管理网上辅导,热招中!!

更多信息请进入:项目管理海量题库  我考网项目管理论坛

上一页12下一页

视频学习

我考网版权与免责声明

① 凡本网注明稿件来源为"原创"的所有文字、图片和音视频稿件,版权均属本网所有。任何媒体、网站或个人转载、链接转贴或以其他方式复制发表时必须注明"稿件来源:我考网",违者本网将依法追究责任;

② 本网部分稿件来源于网络,任何单位或个人认为我考网发布的内容可能涉嫌侵犯其合法权益,应该及时向我考网书面反馈,并提供身份证明、权属证明及详细侵权情况证明,我考网在收到上述法律文件后,将会尽快移除被控侵权内容。

最近更新

社区交流

考试问答