8. To integrate approved scope changes, the PM should begin with:
Approved budget
Project schedule
Human resource requirements
Product description
WBS

为了综合的批准范围变更,项目经理首先应当开始:
批准预算
确定项目进度
寻找人员
产品描述
工作分解结构WBS

9. Change requests are an integral part of a project, and one of the ways a PM controls scope changes. Change requests are a result of:
Changes in quality of a vendor-provided component.
A beneficial change, which occurred after the scope was approved.
An error or omission is the product description.
A “make or buy” decision which was modified.
All of the above

变更要求是一个项目的主要部分,也是项目经理控制范围变更的一种方法. 变更要求是—的结果:
变更卖主提供的成分的质量
一个有益的变更,它发生在范围被批准之后
产品描述的一个错误或遗漏
一个修改的“做或买”的决定
上述所有

10. In a project environment, functional managers are responsible for:
Acting as a sounding board for clarification of critical issues.
Setting ground rules and assumptions
Outlining time, cost and performance constraints.
Identifying and developing mitigation strategies for areas of risk.
Establishing administrative policies

在项目环境下,功能经理的责任是:
充当一个澄清关键问题的宣传媒介
设定基本规则和假设
勾画时间、成本和执行限制的轮廓
确定和完善风险范围内的减轻策略
建立管理政策

相关练习题: 

PMP认证考试练习题(四)(中英文)    

PMP认证考试最新练习题及参考答案汇总

精品推荐:

PMP全真试题精选

欢迎进入在线试听:项目管理网上辅导,热招中!!

更多信息请进入:项目管理海量题库  我考网项目管理论坛

上一页12下一页

视频学习

我考网版权与免责声明

① 凡本网注明稿件来源为"原创"的所有文字、图片和音视频稿件,版权均属本网所有。任何媒体、网站或个人转载、链接转贴或以其他方式复制发表时必须注明"稿件来源:我考网",违者本网将依法追究责任;

② 本网部分稿件来源于网络,任何单位或个人认为我考网发布的内容可能涉嫌侵犯其合法权益,应该及时向我考网书面反馈,并提供身份证明、权属证明及详细侵权情况证明,我考网在收到上述法律文件后,将会尽快移除被控侵权内容。

最近更新

社区交流

考试问答