1. _____ is associated with a buyer's request for materials or equipment to meet a particular need or accomplish a specific purpose.
a. express warranty
b. implied warranty of merchantability
c. implied warranty of fitness for a particular purpose
d. prescribed warranty
e. none of the above.
ans: c来源:www.examda.com

2. adm is an activity-on-arrow method. in this method, a dummy activity:
a. denotes a critical path relationship.
b. denotes any dependency relationship.
c. shows slack.
d. identifies customer deliverables dates.
e. identifies customer team meeting dates.
ans: b

3. an informal communication network on a project and within an organization is called a(n):
a. free upward flow
b. free horizontal flow
c. unrestricted communication flow
d. grapevine
e. open networkwww.Examda.CoM
ans: d

4. by which process may an unsuccessful supplier seek remedy for unjust awards?
a. contract dispute
b. stop work order
c. bid protest
d. coffective action
e. none of the above.
ans: c

205. risk classified as unknown unknowns (i.e., those which cannot be identified or evaluated):
a. should be deflected to the contracting officer
b. should be handled via contingency allowances
c. should be ignored, since they cannot be identified
d. should be ignored, since they are not covered in the project risk assessment
e. c and d
ans: b

6. the "zero defect" concept was proposed by:
a. deming
b. juran
c. crosby
d. tagushi
e. a and d only来源:考
ans: c

7. the major difference between project and line management is that the project manager may not have any control over which basic
management function?
a. decision-making
b. staffing
c. rewarding
d. tracking/monitoring
e. reviewing
ans: b

8. which of the following planning considerations is often overlooked?
a. planning for project termination.
b. qualified project manager assignment.
c. insuring top management support.
d. clearly defined tasks.
e. all of the above.
ans: a

9. a recurring communication pattern within the project organization or company is called a:
a. free-form matrix
b. structured matrix
c. network
d. rigid channel
e. none of the above.来源:www.examda.com
ans: c

10. during a project review meeting, you discover that your $250,000 project has a negative schedule variance of $20,000 which equates to 12%
of the work scheduled to this point of time. you can therefore conclude that:
a. the project will be completed late.
b. the critical path has been lengthened.
c. the costs are being overrun.
d. overtime will be required to maintain the original critical path.
e. none of the above.
ans: e

11. once the logic of a network is laid out, the project manager will conduct a forward pass and backward pass through the network. this will
provide information on the _____ and identification of the _____ .
a. slack for each activity, critical path.
b. slack for each activity, high risk activities.
c. manpower shortages, high risk activities.
d. high risk activities, non-critical paths.
e. manpower availability, contingency plans.
ans: a

12. risk can be divided into two basic types; business risk and pure (or insurable risk). of the following, which one(s) fall(s) under business risk?
a. liability loss
b. direct property loss
c. profit loss
d. personnel-related loss
e. b and c
ans: c

上一页12下一页

视频学习

我考网版权与免责声明

① 凡本网注明稿件来源为"原创"的所有文字、图片和音视频稿件,版权均属本网所有。任何媒体、网站或个人转载、链接转贴或以其他方式复制发表时必须注明"稿件来源:我考网",违者本网将依法追究责任;

② 本网部分稿件来源于网络,任何单位或个人认为我考网发布的内容可能涉嫌侵犯其合法权益,应该及时向我考网书面反馈,并提供身份证明、权属证明及详细侵权情况证明,我考网在收到上述法律文件后,将会尽快移除被控侵权内容。

最近更新

社区交流

考试问答