1. fixed-price and incentive-type contracts place responsibility for performance and financial risks associated with delay or non-performance on
the:
a. buyer
b. third party
c. contractor
d. all of the above
e. none of the above
ans: c来源:考

2. in a contract, the point of total assumption refers to the point where:
a. the customer incurs the total financial responsibility for each additional dollar spent.
b. the contractor incurs the total financial responsiblity for each dollar spent.
c. the schedule and cost variance are zero.
d. the customer will incur no further costs for the work the contractor performs in the completion of the contract.
e. b and d only.
ans: e

3. in a matrix organizational form, mbo may be difficult to implement:
a. if the functional employees are supervised closely by the line manager rather than the project manager
b. unless the project manager has an input into the employee's performance review
c. unless the project and line managers agree on the ultimate objective
d. unless the project and line managers agree to the duration of the task
e. none of the above are correct answers我考网(www.Examda。com)
ans: e

4. quality assurance
a. refers to the prevention of product defects
b. is an auditing function that provides feedback to the project team and client about the quality of output being produced.
c. is the technical process that include the construction of control charts which specify acceptability limits for conforming output.
d. a and b.
e. b and c
ans: b

5. which of the following communication media is least accepted by organizations?
a. tactile
b. audio
c. extrasensory
d. visual来源:考
e. olfactory
ans: c

6. formal written communication is mandated for which of the following?
a. scope changes not part of the original project
b. taking exception to a specification
c. procurement of raw materials
d. all of the above.
e. a and b only
ans: d

7. in performing an impact analysis, the most effective tool to ensure all risks are identified on large projects is the:
a. work breakdown structure
b. milestone review and schedule technique
c. cost/schedule control system
d. planning programming budget system
e. program and evaluation review technique
ans: a

8. in the project environment, the individual ultimately responsible for quality control is:
a. the line workers who must strive "to do things right the first time" to avoid quality problems.
b. the company's quality control manager who must work with the project members to ensure the quality control program is effective.
c. the head of the production department who retains ultimate quality control responsibility for all the company's projects.
d. the project manager who has ultimate responsibility for the entire project.
e. the customer who must ensure that he is receiving a quality product from the vendor.
ans: d

9. in which organizational form do project managers usually get to know the employees well enough to provide an input into their performance
review?
a. expediter
b. coordinator来源:我考网网
c. pure project
d. matrix
e. line-staff
ans: c

10. the critical path in a schedule network is the path that:
a. takes the longest time to complete
b. must be done before any other tasks
c. allows some flexibility in scheduling a start time.
d. is not affected by schedule slippage
e. all of the above.
ans: a

11. the use of the project reports:
a. are not necessary on small projects
b. provides a means whereby various levels of authority can judge project performance
c. provides insight into project areas and the effectiveness of the control systems
d. all of the above
e. b and cwww.Examda.CoM
ans: e

12. you must produce 27 widgets. you can only produce 9 widgets per production run. each production line setup costs $1000. each widget
consumes $10 worth of material and $5 worth of labor. what is the total fixed cost for producing the widgets.
a. 3000
b. 27000
c. 27270
d. 1335
e. 1000
ans: e

上一页12下一页

视频学习

我考网版权与免责声明

① 凡本网注明稿件来源为"原创"的所有文字、图片和音视频稿件,版权均属本网所有。任何媒体、网站或个人转载、链接转贴或以其他方式复制发表时必须注明"稿件来源:我考网",违者本网将依法追究责任;

② 本网部分稿件来源于网络,任何单位或个人认为我考网发布的内容可能涉嫌侵犯其合法权益,应该及时向我考网书面反馈,并提供身份证明、权属证明及详细侵权情况证明,我考网在收到上述法律文件后,将会尽快移除被控侵权内容。

最近更新

社区交流

考试问答