PMP认证考试练习题及参考答案(十九)

来源:项目管理师    发布时间:2012-05-07    项目管理师视频    评论

1. history has shown that project managers can be trained in a combination of ways. which method is usually

preferred by most companies?
a. experiential learning, on-the-job
b. formal education and special course (degreed programs)
c. professional activities, seminars
d. individual readings
e. none of the above我考网(www.Examda。com)
ans: a

2. the purpose of configuration management is to:
a. insure drawings are updated
b. control change throughout the project
c. control change during the production only
d. generate engineering change proposals
e. inform the project manager of changes
ans: b

3. three types of written media used in organizations are _____, _____, and ______.
a. manual, letters, guidelines
b. individually-oriented, legally-oriented, organizationally oriented
c. guidelines, forms, procedures
d. letters, guidelines, brochures来源:考
e. letters, contracts, policies.
ans: d

4. which of the following is considered a direct cost for producing a widget?
a. the cost of the materials used to produce a widget.
b. the labor costs of the workers who actually produced the widget.
c. the rent for the building in which the widget was manufactured
d. the salary of senior management and the project sponsor
e. a and b only
ans: e

5. _____ best describes the goal of a project in its relationship with the customer, from initial contact

through delivery.
a. fitness for use
b. customer satisfaction
c. conformance to requirements
d. fitness for purpose
e. all of the above.来源:我考网网
ans: b

6. a communicator can present information using the following media except:
a. visual
b. audio
c. tactile
d. performal
e. both a and b
ans: d

7. advantages of the functional (hierarchical) form of organization include _____ and creation of technical

competence.
a. ease of horizontal coordination
b. clearly defined authority
c. high information processing capability
d. single voice to customers
ans: b来源:www.examda.com

8. quality and _____ are directly related.
a. productivity
b. cost overruns
c. scope control
d. pareto diagram
e. none of the above.
ans: a

9. resource leveling will often affect the project by making it:
a. shorter.
b. longer
c. more responsive to customer needs.
d. a and c
e. b and c.
ans: b来源:考

10. selection criteria for project selection include:
a. cost versus benefit
b. risk
c. contribution towards organizational goals
d. rate of return
e. all of the above.
ans: e

11. the statement of work (sow) is developed during the _____ cycle.
a. award
b. solicitations
c. requirementswww.Examda.CoM
d. contractual
e. requisitions
ans: c

12. which of the following depreciation methods provides for accelerated depreciation of an asset:
a. double declining balance.
b. straight line.
c. exponential depreciation
d. double sum of the years digits
e. double increasing balance
ans: a

上一页12下一页

视频学习

我考网版权与免责声明

① 凡本网注明稿件来源为"原创"的所有文字、图片和音视频稿件,版权均属本网所有。任何媒体、网站或个人转载、链接转贴或以其他方式复制发表时必须注明"稿件来源:我考网",违者本网将依法追究责任;

② 本网部分稿件来源于网络,任何单位或个人认为我考网发布的内容可能涉嫌侵犯其合法权益,应该及时向我考网书面反馈,并提供身份证明、权属证明及详细侵权情况证明,我考网在收到上述法律文件后,将会尽快移除被控侵权内容。

最近更新

社区交流

考试问答