1. on november 1, $1000 worth of work on task a was supposed to have been done (bcws); however, the bcwp was $850. calculate the
schedule variance:
a. -100
b. 100
c. -150
d. 150
e. 0.85
ans: c

2. the quality risk _____ .
a. is minimized through continuous monitoring.
b. is considered a long term risk.
c. will be reflected in the in-service life of the project result.
d. b and c
e. all of the above.
ans: e来源:www.examda.com

3. the act of conducting or supervising the exchange of information is:
a. consulting
b. project management
c. communications management
d. communications enhancement
e. none of the above
ans: c

4. the core function of the project manager is
a. systems design
b. client interfacing
c. quality assurance
d. integration来源:考
e.
ans: d

5. the future value of an annual income flow of $1000 for 2 years at 10% is:
a. 2200
b. 2280
c. 2300
d. 2310
e. none of the above
ans: d

6. the initial cost of a product and the product's operation and maintenance costs _____ .
a. increases perceived value when balanced.
b. are incidental to each other because initial costs are "sunk"
c. decreases design costs as operation periods increase
d. provides perceived function value and product social dysfunction
e. are integrally related with each other because initial costs are "sunk".
ans: a

7. all of the following may hinder a person's ability to transmit/receive a message except:
a. unfamiliarity with topic
b. withholding information
c. assuming
d. noise我考网(www.Examda。com)
e. preoccupation
ans: a

8. quality improvement programs are normally associated with which two of the following?
a. juran and crosby
b. juran and deming
c. crosby and deming
d. deming and the japanese
e. crosby and the japanese
ans: d

9. the utility theory _____ .
a. considers risk propensity of the decision maker.
b. attempts to formalize management's risk considerations.
c. works well with decision tree analysis.
d. is considered highly theoretical.
e. all of the above.
ans: b

10. the document authorizing functional areas to charge against the project is the:
a. work authorization form
b. scope baseline
c. project charter
d. management plan来源:考
e. linear responsibility chart
ans: a

11. the purpose of a dummy activity in an activity-on-arrow diagram is to:
a. identify a task that could be replaced by another.
b. take the slack time into account.
c. show a task that is not necessarily needed.
d. denote a milestone.
e. show a dependency relationship.
ans: e

12. when planning, organizing, coordinating, and controlling a project an important human resources skill or ability would be
a. building multi-disciplinary teams
b. managing conflict
c. communicating orally and in writing with all levels of personnel
d. involving senior management
e. all are important
ans: e

上一页12下一页

视频学习

我考网版权与免责声明

① 凡本网注明稿件来源为"原创"的所有文字、图片和音视频稿件,版权均属本网所有。任何媒体、网站或个人转载、链接转贴或以其他方式复制发表时必须注明"稿件来源:我考网",违者本网将依法追究责任;

② 本网部分稿件来源于网络,任何单位或个人认为我考网发布的内容可能涉嫌侵犯其合法权益,应该及时向我考网书面反馈,并提供身份证明、权属证明及详细侵权情况证明,我考网在收到上述法律文件后,将会尽快移除被控侵权内容。

最近更新

社区交流

考试问答