1. which of the following is referred to as payback period:
a. the number of periods required to recover the initial investment
b. the rate of return on the investment
c. the number of periods required to bring project cost back to the original budget, based on current performance
d. loan payment schedule
e. none of the above
ans: a

2. which one of the following is not an acquisition method?
a. advertising
b. invitation
c. negotiation
d. purchase我考网论坛
e. all are acquisition methods
ans: a

3. at least _____of the cost of quality are the direct responsibility of management.
a. 0.25
b. 0.85
c. 0.5
d. 1
e. 0.33
ans: b

4. fast tracking means to:
a. speed up a project through parallel tasks.
b. swap one task for another.
c. reduce the number of tasks if possible.
d. b and c.
e. none of the above.
ans: a来源:我考网网

5. formal written correspondence is mandated in which of the following situations:
a. product undergoes casual in-house testing
b. client requests additional work not covered under contract
c. project manager calls a meeting
d. b and c only
e. none of the above
ans: b

6. the delphi method is _____ .
a. used to derive a consensus arriving at a convergent solution
b. useful in determining probability relating to future events.
c. used with questionnaires based on established scenarios.
d. continued as an iterative process until a solution is reached.
e. all of the above.
ans: e

7. the positive value of conflict is underestimated. properly managed, conflict is a valuable tool, particularly when
a. a diversion is needed
b. conflictive situations are in their early stages and emotional involvement is low
c. conflictive situations are in their late stages and emotional involvement is high
d. conflict may cause a loss of status or position power
e.
ans: b

8. under the terms of 2/10 net 30, the buyer may:来源:考
a. deduct 10% of the invoice amount for payment within 30 days
b. deduct 2% of the invoice for payment within 10 days
c. incurs a penalty on 10% for payments more than 30 days late
d. settle the invoice with 2 equal payments; one within 10 days and the other within 30 days
e. none of the above
ans: b

9. which of the following can result in misinterpretation of the statement of work?
a. using imprecise language (i.e. nearly, approximately)
b. mixing tasks, specifications, special instructions and approvals
c. no pattern, structure or chronological order
d. wide variation in the size of tasks or details of work
e. all of the above
ans: e

10. amount at stake is the _____ .
a. function of planned time/real time project costs.
b. risk identified in successful project completions.
c. (standard project deviation + expected costs)/6
d. cost of investment loss + least cost to restore status quo.
e. inherent risk at conception altered by standard project deviations.来源:我考网网
ans: d

11. in communications management, to assimilate through the mind or senses (as in new ideas) is the process of
a. understanding
b. communicating
c. receiving
d. decoding
e. comprehending
ans: c

12. in general, the best long-lasting approach to settling project conflict is the _____ approach .
a. problem solving
b. compromise
c. withdrawal
d. smoothing
e. forcing
ans: a

上一页12下一页

视频学习

我考网版权与免责声明

① 凡本网注明稿件来源为"原创"的所有文字、图片和音视频稿件,版权均属本网所有。任何媒体、网站或个人转载、链接转贴或以其他方式复制发表时必须注明"稿件来源:我考网",违者本网将依法追究责任;

② 本网部分稿件来源于网络,任何单位或个人认为我考网发布的内容可能涉嫌侵犯其合法权益,应该及时向我考网书面反馈,并提供身份证明、权属证明及详细侵权情况证明,我考网在收到上述法律文件后,将会尽快移除被控侵权内容。

最近更新

社区交流

考试问答