PMP认证考试练习题及参考答案(二十四)

来源:项目管理师    发布时间:2012-05-07    项目管理师视频    评论

1 Which of the following can be tracked using the WBS?
A time
B cost
C performance
D scope http://ks.examda.com
E None of the above.
ans:D
2 Which of the following are types of status reports?
A document, variance, trend and exception
B cost, trend, schedule and acquisition
C cost, schedule, technical performance
D analysis, cost, performance and schedule
E All of the above.
ans:C
3 You have been assigned as a project leader and must first review the statement of work provided by the customer. Which of the following is most often overlooked?
A Data item deliverables
B Customer-furnished equipment and facilities
C Long-lead procurement items
D Customer-imposed milestones
E Other subcontractor interface requirements
ans:A
4 During the planning phase of a project, you realize that more than one functional department possesses the skill and technical know-how to perform a given task. The best way for the project manager to handle this would be to:
A Make the decision, document it in the linear responsibility chart, and distribute the chart to all departments.
B Let the affected line groups decide among themselves who will perform the work
C Ask the executive sponsor to make the decision 来源:我考网网
D Allow each line group to perform part of the task
E All of the above
ans:B
5 The most common definition of project success is:
A Within time
B Within time and cost
C Within time, cost and technical performance requirements
D Within time, cost, performance and accepted by the customer/user
E None of the above
ans:D
6 The scope of a project can be expected to change if:
A The project manager must provide cost estimates without having a design concept
B Oversimplification (underestimating) of the nature of the work occurs
C The project manager is assigned after the project is defined, and the cost and schedule are approved
D A clear objective is not provided
E All of the above are possible based upon the situation
ans:E
7 The most common non-behavioral reason for projects being completed behind schedule and over budget is:
A Selecting the wrong person as the project manager
B Selecting the wrong person as the sponsor
C Accepting a high-risk project 我考网(www.Examda。com)
D Ill-defined requirements
E All of the above
ans:D
8 The appointment or selection of a project sponsor is often based upon:
A The strategic importance of the project
B Who the customer is
C Whether the organization is project or non-project-driven
D The profitability of the project
E All of the above
ans:E
9 The "rolling wave" or "moving window" concept is used most frequently on projects where:
A The baseline is frozen for the duration of the project and no scope changes are permitted
B Marketing is unsure of what the customer actually wants and reserves the right to make major scope changes
C The low levels of the work breakdown structure are known with certainty for the next three to six months, but the remaining tasks are based upon the results of the first three to six months of work
D Networking techniques are not appropriate
E All of the above
ans:C
10 Interfacing with the customer after project go-ahead is the responsibility of:
A Project sponsor
B Project team
C Project manager 来源:考
D Functional manager
E All of the above are possible, based upon the size and complexity of the project
ans:C
11 Using the WBS shown in the Special window, a typical work package would be:
A Software development
B Systems design
C Coding
D A, B, and C
E None of the above.
ans:E
12 Feasibility studies evaluate alternatives in terms of
A Cost-effectiveness
B Ease of performance
C Risk
D Safety
E All or part of A through D
ans:E

上一页12下一页

视频学习

我考网版权与免责声明

① 凡本网注明稿件来源为"原创"的所有文字、图片和音视频稿件,版权均属本网所有。任何媒体、网站或个人转载、链接转贴或以其他方式复制发表时必须注明"稿件来源:我考网",违者本网将依法追究责任;

② 本网部分稿件来源于网络,任何单位或个人认为我考网发布的内容可能涉嫌侵犯其合法权益,应该及时向我考网书面反馈,并提供身份证明、权属证明及详细侵权情况证明,我考网在收到上述法律文件后,将会尽快移除被控侵权内容。

最近更新

社区交流

考试问答