1 Historical records during close-out are useful to _____ and _____ for future projects.
A Predict trends, highlight problems.
B Analyze successes, shortfalls.
C Analyze strengths, document results.
D Support litigation, defend claims.
E Justify results, set standards.
ans:A
2 A clear definition of the user's needs serves as the direct basis for the:
A Work breakdown structure.
B Functional requirements.
C Project cost estimate. 来源:www.examda.com
D Selection of personnel.
E Termination decision.
ans:B
3 Middle (functional) managers have the greatest influence in the direction of the project in which type of organizational structure?
A Project.
B Strong matrix.
C Weak matrix.
D Project coordinator. 来源:www.examda.com
E Project expeditor.
ans:C
4 The project charter:
A Expresses upper management commitment to the project.
B Provides that authority by which the project will be run.
C Establishes that organizational structure with the project.
D Specifies overall objectives and timeframe of the project.
E All of the above.
ans:E
5 The WBS is:
A An organization oriented family tree of the project.
B A task oriented family tree of the project.
C A cost centered structure of the project.
D Only required on large complex projects where separately identifiable work packages are difficult to construct.
E None of the above. 来源:考
ans:B
6 Including the customer in the process of project planning is:
A Slow and counterproductive.
B Essential in the definition and documentation of project goals.
C Necessary, but of limited value.
D Unnecessary because project goals are defined in the proposal stage.
E None of the above.
ans:B
7 The scope management provides:
A A basis for future decisions about the project.
B A baseline to accomplish verification measures.
C A baseline to evaluate potential scope changes.
D All of the above.
E B and C only. 我考网论坛
ans:D
8 During project execution, a line manager informs you that he will not have sufficient resources available next month to support your and two other projects. The best way to handle this problem would be to:
A Ask the line manager to make the decision.
B Ask the line manager to work with senior management to prioritize the work.
C Ask your sponsor to meet with the line manager.
D Ask the line manager to set up a meeting with you and the other project managers to work out the problem yourselves.
E Prepare a purchase order to outsource the work.
ans:D
9 Proper implementation of project management will guarantee that:
A Budgets will be met.
B Schedules will be adhered to.
C Quality/performance will be met.
D The project will be a success. 我考网(www.Examda。com)
E None of the above.
ans:E
10 The most difficult decision for the executive sponsors to make at the end-of-phase review meeting is:
A Budget allocations for the next phase.
B Authorizing scope changes for the next phase.
C Authorizing budget increases for the next phase based upon scope changes.
D Canceling the project.
E All of the above.
ans:D
11 The financial closeout of a project dictates that:
A All project funds have been spent.
B No charge numbers have been overrun.
C No follow-on work from this client is possible.
D No further charges can be made against the project.
E All of the above.
ans:D
12 A project can best be defined as:
A Series of non-related activities designed to accomplish single and multiple objectives.
B Coordinated effort of related activities designed to accomplish a goal without a well-established end point.
C Cradle-to-grave activities which must be accomplished in less than one year and consumes human and non-human resources.
D Any undertaking with a definable time frame, well-defined objectives, and consumes both human and non-human resources with certain constraints.
E All of the above.
ans:D

上一页12下一页

视频学习

我考网版权与免责声明

① 凡本网注明稿件来源为"原创"的所有文字、图片和音视频稿件,版权均属本网所有。任何媒体、网站或个人转载、链接转贴或以其他方式复制发表时必须注明"稿件来源:我考网",违者本网将依法追究责任;

② 本网部分稿件来源于网络,任何单位或个人认为我考网发布的内容可能涉嫌侵犯其合法权益,应该及时向我考网书面反馈,并提供身份证明、权属证明及详细侵权情况证明,我考网在收到上述法律文件后,将会尽快移除被控侵权内容。

最近更新

社区交流

考试问答