1 The cost of a quality program should be budgeted at _____ of the total project.
A 10-12%
B 2-3 %
C 6-8%
D 3-5%
E more than 15 %
ans:D
2 _____ of the extra costs of the project can often be attributed to a lack of quality.
A 12%
B 15%
C 20%
D 25%
E less than 10% 来源:考
ans:C
3 CIP embodies which of the following principals?
A constancy of purpose
B customer focus and involvement
C total involvement
D teamwork
E All of the above.
ans:E
4 The key ingredient to a successful quality management program are _____.
A management's quality philosophy, operational quality assurance and operational quality control.
B quality evaluation methods and functional quality integrators.
C technical quality administration, the technical quality specifications, and the quality process review.
D quality evaluation methods, quality progress reviews and the technical quality specifications.
E All of the above.
ans:A
5 At least _____of the cost of quality are the direct responsibility of management.
A 25%
B 85%
C 50%
D 100%
E 33%
ans:B
6 Non-conformance penalties are a form of _____.
A quality incentive
B risk sharing
C contract negotiations
D quality assurance programs
E None of the above. www.Examda.CoM
ans:C
7 Quality Improvement Programs are normally associated with which two of the following?
A Juran and Crosby
B Juran and Deming
C Crosby and Deming
D Deming and the Japanese
E Crosby and the Japanese
ans:D
8 The initial cost of a product and the product's operation and maintenance costs _____ .
A increases perceived value when balanced.
B are incidental to each other because initial costs are "sunk"
C decreases design costs as operation periods increase
D provides perceived function value and product social dysfunction
E are integrally related with each other because initial costs are "sunk".
ans:A
9 Quality control is normally performed by the _____ .
A QA personnel
B project team
C operating personnel
D project management
E None of the above.
ans:C
10 Quality and _____ are directly related.
A productivity
B cost overruns
C scope control 我考网(www.Examda。com)
D Pareto diagram
E None of the above.
ans:A
11 _____ best describes the goal of a project in its relationship with the customer, from initial contact through delivery.
A fitness for use
B customer satisfaction
C conformance to requirements
D fitness for purpose
E All of the above.
ans:B
12 The primary consideration of product management is to know the _____.
A probability of product's performance with specified parameters
B ability the product has to perform its intended function
C ability of a product to be produced within existing parameters
D functionality the product will provide over its useful life
E All of the above
ans:D

上一页12下一页

视频学习

我考网版权与免责声明

① 凡本网注明稿件来源为"原创"的所有文字、图片和音视频稿件,版权均属本网所有。任何媒体、网站或个人转载、链接转贴或以其他方式复制发表时必须注明"稿件来源:我考网",违者本网将依法追究责任;

② 本网部分稿件来源于网络,任何单位或个人认为我考网发布的内容可能涉嫌侵犯其合法权益,应该及时向我考网书面反馈,并提供身份证明、权属证明及详细侵权情况证明,我考网在收到上述法律文件后,将会尽快移除被控侵权内容。

最近更新

社区交流

考试问答