Qustions 1:
A change control system should include all the following except-

a.Procedures for automatic approval of defined categories of change
b. Paperwork, tracking systems, and approval levels necessary for authorizing changes
c. A description of the powers and responsibilities of the change control board
d. Procedures for conducting a midproject control system review

Qustions 3:

Two fundamental objectives of project control are to--

a. Alter activities to achieve results and manage organizational assets
b. Eliminate unexpected technical problems and identify technical difficulties that require more resources
c. Ensure that resources are available when needed and avoid increases in the scope of work
d. Have the required material, personnel, and equipment available when needed and ensure that budgeting is adequate

Qustions 5:

The project plan is important in change control because it--

a.Provides the baseline against which changes are managed
b. Provides the information on project performance
c. Alerts the project team to issues that may cause problems in the future
d. Is expected to change throughout the project

Qustions 2:
Written changes orders should be required on --

a. All projects, large and small
b. Large projects
c. Projects with a formal configuration management system in place
d. Projects for which the cost of a change control system can be justified

Qustions 4:

The principal sources of project failure are-


a. Lack of a projectized or strong matrix structure, poor scope definition, and lack of a project plan
b. Lack of commitment or support by top management, disharmony on the project team, and lack of leadership by the project manager
c. Poorly identified customer needs, a geographically dispersed project team, and little communication with the customer until the project is delivered
d. Organizational factors, poorly identified customer needs, inadequately specified project requirements, and poor planning and control

Qustions 6:

Interface management is --

a.Considered to be one of the easier aspects of implementing the project plan
b.Primarily concerned with the technical issues associated with linking system components in a configuration
c.Facilitated by use of the WBS to display the ways people on the project interact and their duties and responsibilities
d.The process of coordinating the various elements of the project so that they meet their joint goals of performance, schedule, and budget

视频学习

我考网版权与免责声明

① 凡本网注明稿件来源为"原创"的所有文字、图片和音视频稿件,版权均属本网所有。任何媒体、网站或个人转载、链接转贴或以其他方式复制发表时必须注明"稿件来源:我考网",违者本网将依法追究责任;

② 本网部分稿件来源于网络,任何单位或个人认为我考网发布的内容可能涉嫌侵犯其合法权益,应该及时向我考网书面反馈,并提供身份证明、权属证明及详细侵权情况证明,我考网在收到上述法律文件后,将会尽快移除被控侵权内容。

最近更新

社区交流

考试问答