Qustions 1: 
The change control system includes-- 

a. Procedures to define how documents may be changed 
b. Specific change requests expected on the project and plans to respond to each one 
c. Performance reports that forecast project changes 
d. A description of the functional and physical characteristics of an item or system 

Qustions 3:

Typically, change control systems include automatic approval of certain types of changes. An example of such a change is one that is--

a.  Suggested by the project sponsor 
b. The result of an emergency 
c. Suggested by the customer 
d. Made mandatory by a new regulation 

Qustions 5:

Rolling wave planning provides information on the work to be done--


a.
Throughout all phases of the project

b. For successful completion of the current phases of the project 
c. For successful completion of the current phase and subsequent phases of the project 
d. In the next phase of the project 

Qustions 2: 
According to Herzberg’s motivator-hygiene Theory of Motivation, if achievement, recognition, responsibility, advancement or promotion, and positive supervisor attitude are not present, employees will-- 

a. Become alienated with the organization and leave 
b. Lack motivation but will not be dissatisfied with their work 
c. Lack motivation and become dissatisfied with their work 
d. Become dissatisfied only if they do not receive salary increases 

Qustions 4:

Problem solving, which is an important activity on projects, consists of --

a. Influencing the organizations to get things done 
b. Defining problems and making decisions 
c. Conferring with others to reach a dicision 
d. Producing key results expected by stakeholders 

Qustions 6:

Configuration management describes procedures to apply technical and administrative direction. Which of the following tasks is not performed in configuration management -- 

a.
Identifying functional and physical characteristics of an item or system 
b.
Controlling changes to characteristics 
c.
Performing an audit to verifiy conformance to requierments
d.
Allowing automatic approval of changes 
 

视频学习

我考网版权与免责声明

① 凡本网注明稿件来源为"原创"的所有文字、图片和音视频稿件,版权均属本网所有。任何媒体、网站或个人转载、链接转贴或以其他方式复制发表时必须注明"稿件来源:我考网",违者本网将依法追究责任;

② 本网部分稿件来源于网络,任何单位或个人认为我考网发布的内容可能涉嫌侵犯其合法权益,应该及时向我考网书面反馈,并提供身份证明、权属证明及详细侵权情况证明,我考网在收到上述法律文件后,将会尽快移除被控侵权内容。

最近更新

社区交流

考试问答