Disclaimer: These questions are intended for study purposes only. Success on these questions is not indicative of success on the Project Management Professional Certification Examination. This download of the Sample Exam Questions is for your personal use and NOT FOR commercial use. Any unauthorized use or duplication of this document is prohibited!
1. A narrative description of products or services to be supplied under contract is called:
a. The project plan.
B. A statement of work.
C. An exception report.
D. A Pareto analysis.
2. An example of scope verification is:
a. Reviewing the performance of an installed software module.
B. Managing changes to the project schedule.
C. Decomposing the WBS to a work package level.
D. Performing a benefit/cost analysis to determine if we should proceed with the pro
3. Which of the following is not an example of a source of scope change?
A. A variation in government regulations.
B. Failure to include a required feature in the design of a telecommunication system.
C. A need to engage in bottom-up cost estimating.
D. Introducing technology that was not available when scope was originally defined.
4. The subdivision of major project deliverables, as identified in the scope statement, into smaller, more manageable components is called:
a. Parametric estimation.
B. Scope definition.
C. Feasibility analysis.
D. Benefit-cost analysis.
5. The process of establishing clear and achievable objectives, measuring their achievement, and adjusting performance in accordance with the results of the measurement is called:
a. Strategic planning.
B. Alternative objectives inventory.
C. Management by objectives.
D. Contingency planning.
6. Configuration management is:
a. Used to ensure that the description of the project product is correct and complete.
B. The creation of the work breakdown structure.
C. The set of procedures developed to assure that project design criteria are met.
D. A mechanism to track budget and schedule variances.
7. A fundamental tenet of modern quality management holds that quality is most likely to be achieved by:
a. Planning it into the project.
B. Developing careful mechanisms to inspect for quality.
C. Striving to do the best job possible.
D. Conducting quality circle activities.
8. Your most recent project status report contains the following information: BCWP = 3,000, ACWP = 3,500, and BCWS = 4,000. The schedule variance is:
a. + 1,000.
B. + 500.
C. - 500.
D. - 1,000.
9. Learning curve theory emphasizes that in producing many goods:
a. Cost decreases as production rates increase.
B. Average unit cost decreases as more units are produced.
C. Materials become cheaper when they are purchased in bulk.
D. Laborers become more productive because of technological advances.
10. Rearranging resources so that constant resource levels are maintained is called:
a. Floating. 
B. Leveling.
C. Restructuring.
D. Crashing.

上一页12345下一页

视频学习

我考网版权与免责声明

① 凡本网注明稿件来源为"原创"的所有文字、图片和音视频稿件,版权均属本网所有。任何媒体、网站或个人转载、链接转贴或以其他方式复制发表时必须注明"稿件来源:我考网",违者本网将依法追究责任;

② 本网部分稿件来源于网络,任何单位或个人认为我考网发布的内容可能涉嫌侵犯其合法权益,应该及时向我考网书面反馈,并提供身份证明、权属证明及详细侵权情况证明,我考网在收到上述法律文件后,将会尽快移除被控侵权内容。

最近更新

社区交流

考试问答