  ● ___(66)___ is a method of constructing a project schedule network diagram that uses boxes or rectangles,referred to as nodes,to represent activites and connects them with arrows that asow the dependencies. 
  This method includes following types of dependcies orprecedence relationships: 
  ___(67)___the initiation of the successor activity, depends upon the completion of the predecessor activity.
  ___(68)___the initiation of the successor activity, depends upon the initiation of the predecessor activity.
  (66) A.PDM        B.CPM       C.PERT      D.AOA
  (67) A.F-S        B.F-F       C.S-F       D.S-S
  (68) A.F-S        B.F-F       C.S-F       D.S-S 

  ● estimating schedule activity costs involves developing an ___(69)___ of the cost of the resources needed to complete each schedule activity. Cost estimating includes identifying and considering various costing alternatives.for example,in mostapplication areas,additional work during a design phase is widely held to have the potential for reducing the cost of the execution phase and product oprations. the cost estimating process considers whether the expected savings can offset the cost of the additional design work. cost estmates are generally expressed in units of ___(70)___ to facilitate comparisons both within and across projects. the ___(71)___ describes important information about prject requirement that is considered duing cost estimating.
  (69) A.accuracy   B.approxination   C.specification  D.summary
  (70) A.activity   B.work        C.currency     D.time
  (71) A.project scope statement    B.statement of work
     C.project management plan    D.project policy 

  ● The ___(72)___ technique involves using project characteristics in a mathematical model to predict total project cost.models can be simple or complex. 
  (72) A.cost aggregation        B.reserve analysis 
     C.parametric estimating D.funding limit reconciliarion 

  ● ___(73)___ is ameasurable, verifiable work poduct such as specification.feasibility study report, detail document, or working prototype 
  (73) A.milestone  B.deliverable  C.etc    D.BAC 

  ● ___(74)___ are individuals and organizations that are actively involved in the project, or whose interests may be affected as aresult of project execution or project completion; they may also exert influence over the project and its results. 
  (74) A.controls          B.baselines
     C.project stakeholders    D.project managers 

  ● ___(75)___ is the process of obtaining the stakeholdrs’formal acceptance of the completed project scope .verifying the scope includes reviewing deliverables and work results to ensure that all were completed satisfactorily.
  (75) A.project acceptance     B.scope verification
     C.scope definition      D.WBS Creation

视频学习

我考网版权与免责声明

① 凡本网注明稿件来源为"原创"的所有文字、图片和音视频稿件,版权均属本网所有。任何媒体、网站或个人转载、链接转贴或以其他方式复制发表时必须注明"稿件来源:我考网",违者本网将依法追究责任;

② 本网部分稿件来源于网络,任何单位或个人认为我考网发布的内容可能涉嫌侵犯其合法权益,应该及时向我考网书面反馈,并提供身份证明、权属证明及详细侵权情况证明,我考网在收到上述法律文件后,将会尽快移除被控侵权内容。

最近更新

社区交流

考试问答