   81. You have had your Scope Definition approved and are working on your budget and schedule. In order to estimate the labor costs and the schedule you need to know who your team members are, and what their skill level is. You consult your staffing managenrnt plan and your staffingpool escription By following the recruitment practices and working with the procurement department to negotiate for arious external contractors you are able to complete a project directory. All these are steps in what process?
          A. Organizational Planning
          B. Resource Planning
          C. Team Development
          D. Staff Acquisition

          82.The primary conmunication skills you will use in working with members of your project team will be:
          A. Problem solving
          B. Negotiating
          C. Team building
          D. Public relations

          83.The primary conmunication skills you will use in working with your project sponsor will be:
          A. Problem solving
          B. Negotiating
          C. Team building
          D. Public relations

          84.The primary conmunication skills you will use in working with functional managers will be:
          A. Problem solving
          B. Negotiating
          C. Team building
          D. Public relations

          85.The primary conmunication skills you will use in working with external stakeholders will be:
          A. Problem solving
          B. Negotiating
          C. Team building
          D. Public relations

          86.According to A H. Maslow, people~ needs must be satisfied according to a certain hierarchy.The order in which needs must be satisfied is:
          A. Self-actualization, esteem, social, safety, physiological
          B. Physiological, seW-actualization, social, esteem, safety
          C. Physiological, safety, social, esteem, self-actualization
          D. Self-actualization, social, physiological, safety, esteem

          87.According to C. P. Alderfer, people~ needs fall into three broad categories. Which of the following is not one of Alderfer抯 categories?
          A. Existence needs
          B. Identity needs
          C. Relatedness needs
          D. GroMh needs

          88.Your project plan requires personnel to wear a Radiation Monitor counter at all times while they are within the protected area surrounding a nuclear reactor. This requirement arises from your concern for:
          A. Quality assurance reporting requirenrnts
          B. Personnel safety needs
          C. Stakeholder reporting requirements
          D. Personnel physiological needs

          89.A staffing management plan includes all of the following except:
          A. Determining how to bring team members onto the project
          B. A resource histogram
          C. Determining how to release team members from the project
          D. Documentation on who has the authority to make decisions

上一页123下一页

视频学习

我考网版权与免责声明

① 凡本网注明稿件来源为"原创"的所有文字、图片和音视频稿件,版权均属本网所有。任何媒体、网站或个人转载、链接转贴或以其他方式复制发表时必须注明"稿件来源:我考网",违者本网将依法追究责任;

② 本网部分稿件来源于网络,任何单位或个人认为我考网发布的内容可能涉嫌侵犯其合法权益,应该及时向我考网书面反馈,并提供身份证明、权属证明及详细侵权情况证明,我考网在收到上述法律文件后,将会尽快移除被控侵权内容。

最近更新

社区交流

考试问答