PMP认证考试试题精选(6.2)

来源:项目管理师    发布时间:2012-05-06    项目管理师视频    评论

        16. A contractor is working on a fixed price contract that calls for a single, lump sum payment upon satisfactory completion of the contract. About halfway through the contract, the contractor’s project manager informs their contract administrator that financial problems are making it difficult for them to pay their employees and subcontractors. The contractor asks for a partial payment for work accomplished. Which of the following actions by the buyer is most likely to cause problems for the project?
          a. starting partial payments for work accomplished.
          b. adhering to the contract and making no early payments.
          c. paying for all work accomplished to date only.
          d. demanding penalty free options to make early payments.

          17. To be successful, negotiating must be conducted in an atmosphere of:
          a. flexibility and understanding.
          b. sincerity and thoughtfulness.
          c. mutual respect and cooperation.
          d. sincerity and prudent caution.

          18. Inputs to cost budgeting include all of the following except:
          a. cost baseline.
          b. cost estimates.
          c. work breakdown structure.
          d. project schedule.

          19. A precise description of a deliverable includes a:
          a. specification.
          b. baseline.
          c. work package.
          d. WBS element.

          20. Theory X management is based upon an assumption that:
          a. quality improvements lie in the hands of quality circles.
          b. profits are tied to meeting the project’s baseline milestones.
          c. absenteeism is tied to poor working conditions.
          d. workers are inherently unmotivated and need strong guidance.

          21. All of the following are characteristics of parametric estimating except:
          a. historical data inputs.
          b. quantifiable relationships.
          c. scalable calculations.
          d. international standards.

          22. Of the following estimates, which most accurately reflect the actual cost of the project?
          a. bottom-up estimates.
          b. order of magnitude estimates.
          c. preliminary estimates.
          d. conceptual estimates.

          23. Including a contingency reserve in the project budget is intended to:
          a. reduce the probability of scope changes.
          b. increase the effectiveness of scope controls.
          c. reduce the probability of a cost overrun.
          d. increase the effectiveness of cost controls.

上一页12下一页

视频学习

我考网版权与免责声明

① 凡本网注明稿件来源为"原创"的所有文字、图片和音视频稿件,版权均属本网所有。任何媒体、网站或个人转载、链接转贴或以其他方式复制发表时必须注明"稿件来源:我考网",违者本网将依法追究责任;

② 本网部分稿件来源于网络,任何单位或个人认为我考网发布的内容可能涉嫌侵犯其合法权益,应该及时向我考网书面反馈,并提供身份证明、权属证明及详细侵权情况证明,我考网在收到上述法律文件后,将会尽快移除被控侵权内容。

最近更新

社区交流

考试问答